The fire alarm record of completion is the NFPA 72 document that confirms the alarm system was installed and tested as designed. Its sprinkler counterpart is the Contractor’s Material and Test Certificate under NFPA 13. Together with the test reports and as-built drawings, these are what prove to the consultant, the owner and the authority that a system is ready for handover.
For how conventional and addressable systems compare, see our guide to choosing a fire alarm system for Saudi projects.
This guide covers the documents NFPA 72 and NFPA 13 expect at acceptance, who prepares them, how long the owner keeps them, and how to prepare them before the approval visit. AZEIDK handles this stage through its testing and commissioning and documentation and final handover services.
Key points
- Chapter 7 of NFPA 72 (2019) sets minimum fire alarm documentation, including a completed record of completion per 7.5.6 and 7.8.2.
- It also includes a sequence of operation (narrative or input/output matrix), a copy of the site-specific software, record drawings and the record of inspection and testing.
- NFPA 13 documentation includes the Owner’s Information Certificate, Contractor’s Material and Test Certificates for aboveground and underground piping, and general information and hydraulic data signs.
- Under NFPA 25 (4.3.5), acceptance and initial records are kept for the life of the installation.
- These documents do not replace Civil Defense and Salamah requirements, but they are the technical basis for installation certificates.
In this article
What is a fire alarm record of completion?
It is a form the contractor completes after installation and testing, summarising the system as actually built: panel type and software, device counts and types, power supplies and batteries, signal transmission and test results. It links the approved design to what is really on site, so the owner and future maintenance teams know exactly what the building contains.
Electrical Contractor magazine, explaining the NFPA 72-2019 documentation rules, notes they apply even if the authority does not raise them. The minimum includes, among other items:
| Document | NFPA 72 (2019) reference | Practical note |
|---|---|---|
| Sequence of operation (narrative or input/output matrix) | 7.4.9 | A matrix is clearer for programmers and reviewers |
| Completed record of completion | 7.5.6 and 7.8.2 | Completed after testing, not before |
| Site-specific software copy with access instructions and passwords | Chapter 7 minimum list | Without it, future maintenance depends on the original contractor |
| Record (as-built) drawings | Chapter 7 minimum list | Must match the panel addresses |
| Records and retention | Section 7.7 | Sets retention periods |
| Completed record of inspection and testing | 7.6.6 and 7.8.2 | Test result for every device |
Contractor’s Material and Test Certificate for sprinklers
According to the National Fire Sprinkler Association (NFSA), NFPA 13 documentation includes the Owner’s Information Certificate (4.2) and Contractor’s Material and Test Certificates for aboveground and underground piping (Chapters 28 and 29), plus general information, hydraulic data and control valve signage, all kept by the owner for the life of the system. The certificates record the materials used (pipe, fittings, sprinklers, valves) and the acceptance results; NFSA lists hydrostatic, flushing, main drain and alarm tests among acceptance records. See our guides to sprinkler acceptance tests and fire alarm commissioning for how the tests are run.
Who prepares and reviews these documents?
- Installing contractor: prepares the record of completion, material and test certificates and test records.
- Consultant or supervisor: witnesses or reviews tests and checks documents against approved drawings and the material submittal.
- Owner: receives and keeps the file and passes it to the maintenance contractor.
- Authority: in Saudi Arabia approval follows Civil Defense and Salamah procedures. AZEIDK issues the safety equipment installation certificate as part of Civil Defense approval support, and handles the technical report through an approved engineering consultancy office.
How long must the owner keep them?
NFSA summarises retention as follows: acceptance and initial records for the life of the installation under NFPA 25 (4.3.5); NFPA 13 documentation for the life of the system; at least three years on the premises or another approved location under the International Fire Code; and periodic NFPA 25 records until one year after the next occurrence of the same type. NFSA adds that the locally adopted code governs and local amendments may change these periods. Our guide to the fire safety log book helps organise records after handover.
Checklist before the acceptance visit
- Complete all device tests and the sprinkler hydrostatic, flushing and main drain tests before filling any form.
- Match device counts in the form with the panel program and as-built drawings.
- Attach the cause-and-effect matrix: alarm, HVAC shutdown, elevator recall, door release, smoke control.
- Record the primary supply and the batteries as installed.
- Collect the aboveground and underground sprinkler certificates and hydraulic sign data.
- Hand the site-specific software and access instructions to the owner in a sealed envelope.
- Obtain signatures and dates from whoever performed and witnessed each test.
- Keep two sets: one in the building near the panel or fire command center, one with the owner.
How this differs from the handover file
The full handover file includes as-builts, O&M manuals, warranties and training, covered in our article on fire systems handover documents. The record of completion and test certificates are the part that proves the test result, so they are usually needed before provisional acceptance.
Common mistakes that delay approval
- A record of completion filled in before testing or copied from another project.
- Device counts that do not match the programmed addresses.
- No sequence of operation, so elevator, HVAC and door interfaces cannot be proven.
- Software and passwords not handed to the owner.
- Sprinkler certificates without the pressure test result or the witness signature.
- Materials that differ from the approved material submittal.
FAQ
What is a fire alarm record of completion?
An NFPA 72 form documenting the system as installed and its test results, completed by the contractor after installation and testing.
What is the Contractor’s Material and Test Certificate?
An NFPA 13 certificate prepared by the sprinkler contractor, one for aboveground and one for underground piping, recording materials and acceptance test results.
Does Civil Defense ask for the record of completion?
We found no published official text naming it. It is part of the NFPA 72 minimum documentation and consultants usually request it in the acceptance file.
How long are acceptance records kept?
For the life of the installation under NFPA 25 (4.3.5), subject to the locally adopted code.
Record of completion or record of inspection and testing?
The record of completion describes the system as built and is prepared once at acceptance; the inspection and testing record documents device test results and repeats with every periodic inspection.
Summary
A passed test is not enough if it is not documented. The fire alarm record of completion and the sprinkler material and test certificates are the written proof that a system was built and tested as designed, and the first thing asked for at any review, renewal or change of maintenance contractor.
Related reading: Fire Alarm in Car Workshops, Voice Sounders for Fire Alarm Systems and Fire Alarm System for Banks.
Approaching handover? Send us the systems scope and test status, and the AZEIDK team will prepare the tests, documentation and handover file. Contact AZEIDK
See the fire alarm panels and systems AZEIDK supplies.
Related guides
- Hotel Fire and Life Safety in Saudi Arabia: Engineering Guide
- Requirements for Restaurants in Malls in Saudi Arabia: Hood Suppression, Mall Fire Alarm Interface and Landlord Approval
- Hotel Access Control: Staff Areas, Stores, Lift Card Control and CCTV Integration
- Parking Barrier and Turnstile Maintenance: Common Faults (Boom, Sensors, Loops, Motor), Periodic Checks and Contract Scope