Building Occupancy Certificate on Balady in Saudi Arabia: Conditions, Steps and the Fire System Documents Needed Before Occupancy

Building Occupancy Certificate on Balady in Saudi Arabia: Conditions, Steps and the Fire System Documents Needed Before

A building occupancy certificate is the municipal document confirming a building was completed according to its permit and approved requirements, and under the executive regulation of the Saudi Building Code enforcement law the building may not be occupied before it is issued. It is now issued electronically on Balady through an application handled by an engineering office, which prepares the engineering report, and approved by the municipality.

For the steps to obtain the Salamah certificate from Civil Defense on the Salamah platform, see our guide; our page on Saudi Civil Defense requirements covers the general requirements for buildings and facilities.

This article sets out the service conditions and steps as published by the Ministry of Municipalities and Housing, then focuses on the fire contractor’s part: the tests, drawings and documents that should be ready before applying. AZEIDK prepares the fire systems handover file through its documentation and final handover service.

Key points

  • A building may not be occupied before the municipality issues the occupancy certificate.
  • The application is made on Balady; the engineering office completes the data and report; the municipality reviews and approves, and the certificate is issued once fees are paid.
  • Published conditions include a building permit issued six months or more earlier, an accredited engineering office for non-residential projects, and a latent defects insurance policy where the regulations require it.
  • The regulation lists final inspection and test approvals and as-built drawings with the application, and the certificate states whether fire safety systems are provided.
  • After the occupancy certificate, a building compliance certificate can be issued automatically.
In this article
  1. What is an occupancy certificate and when do you need it?
  2. Occupancy certificate conditions on Balady
  3. Application steps
  4. Occupancy certificate for part of a building
  5. What the fire contractor hands over before the application
  6. Who does what in the occupancy file?
  7. Fire system issues that delay the occupancy certificate
  8. Occupancy certificate and Civil Defense licensing
  9. FAQ

What is an occupancy certificate and when do you need it?

The executive regulation of the Saudi Building Code enforcement law states that a building may not be occupied until the municipality issues the occupancy certificate, classified by the SBC 201 occupancy classification. The permit holder applies after completion with the permit, final inspection and test approvals and as-built drawings. The certificate records the permit number and date, address and classification, use and occupancy, and whether fire safety systems are provided.

A temporary certificate of up to 180 days may be issued for temporary, seasonal and event buildings and for worker housing on large projects during construction, provided occupancy is safe and code compliant. The full regulation is covered in Saudi Building Code enforcement law.

Occupancy certificate conditions on Balady

On 28 September 2026 the Ministry announced electronic issuance of occupancy certificates on Balady without visiting the municipality. The conditions published in the announcement and service page are:

  • A valid building permit issued six months or more earlier.
  • No occupancy certificate previously issued for the same permit.
  • Service fees and any outstanding debts paid.
  • An accredited engineering office for non-residential projects.
  • A latent defects insurance policy in line with applicable regulations.

Application steps

  1. Log in to the Balady dashboard, choose the user role and start a new application.
  2. Select the owner and applicant type and the building permit concerned.
  3. Choose the engineering office and send the application to it.
  4. The engineering office completes the technical requirements and uploads its engineering report.
  5. The municipality reviews the application, verifies it on site and approves it.
  6. A payment invoice is issued; after payment the certificate can be printed.

The service page lists a processing time of 1 to 10 days, with fees from the platform fee calculator. Once the occupancy certificate is issued and paid, the building compliance certificate can be issued automatically.

Occupancy certificate for part of a building

Balady has a separate service for a building component, used when the certificate is requested for part of a building (a building component) rather than the whole permit. It requires an issued building permit assigned to the supervising engineering office, which enters the permit number, a description of the component and the reason for a partial certificate, accepts the undertakings and sends the request to the municipality. Fire systems serving that part must be complete and tested: partial occupancy does not mean partial protection.

What the fire contractor hands over before the application

The engineering report reflects what was actually built, and the regulation asks for final inspection and test approvals and as-built drawings. For fire systems that means a file built during construction, not after it:

DocumentPurposeFurther reading
Pressure test records for suppression networksProve network integrity before operationhydrostatic testing
Fire alarm testing and commissioning reportsProve detectors, panel and interfaces workfire alarm commissioning
As-built drawingsRecord what was actually installedfire systems handover documents
O&M manuals and datasheetsLet the owner operate and maintain the systemsHandover documents
Warranty certificates and acceptance recordFix the warranty start and contractor responsibilityfire system warranty

AZEIDK carries out fire system testing and commissioning, records the results and compiles the handover file so it is ready when the engineering report is prepared.

Who does what in the occupancy file?

PartyRole in the application
Owner or permit holderApplies on Balady, selects the engineering office, pays fees and provides the latent defects insurance where required
Engineering officeCompletes the technical requirements and uploads the engineering report
MunicipalityReviews the application and approves the certificate
Fire systems contractorHands over test results, as-built drawings and O&M manuals the report relies on

Fire system issues that delay the occupancy certificate

  • Leaving network and alarm tests until after finishes, then finding a leak or fault that means opening ceilings.
  • As-built drawings that no longer match the site after undocumented changes.
  • A complete alarm system whose interfaces with lifts, HVAC and smoke fans were never tested.
  • Missing O&M manuals or datasheets for some equipment.
  • Requesting partial occupancy while that area depends on a pump room or alarm panel in an unfinished part.

Avoiding them starts with a clear test schedule from the start of installation and drawings updated as work progresses.

Occupancy certificate and Civil Defense licensing

The occupancy service page and the Ministry announcement do not list Civil Defense among the conditions. The executive regulation, however, gives Civil Defense oversight of fire code requirements in construction and operation, and any activity occupying the building later needs its own licence on Salamah. Fire systems should therefore be complete, tested and documented when the occupancy certificate is requested, so work is not repeated when tenants and activities are licensed. Project stages up to the Civil Defense certificate are covered in fire protection project timeline.

FAQ

Can a building be used before the occupancy certificate?

No. The executive regulation states a building may not be occupied until the municipality issues the occupancy certificate.

How long does the Balady occupancy certificate take?

The service page lists 1 to 10 days, after the engineering report, municipal approval and payment.

Do I need an engineering office?

Yes for non-residential projects; the office completes the technical requirements and uploads the engineering report.

What is the difference between occupancy and compliance certificates?

The occupancy certificate is issued after completion to the permit; after it, the building compliance certificate can be issued automatically.

Does the certificate mention fire systems?

Yes. The regulation lists whether fire safety systems are provided among the certificate data.

Must the building permit be a certain age?

Yes. The Ministry lists a permit issued six months or more earlier, with no previous occupancy certificate on it.

When should the fire contractor prepare the handover file?

During construction, since the engineering report relies on test results, as-built drawings and O&M manuals.

Can part of a building get an occupancy certificate?

Yes, through the building component service submitted by the supervising engineering office with the reason for the request.

Close to applying for the occupancy certificate? Send us the building type and installed fire systems, and AZEIDK will review the tests and as-built drawings and prepare the handover file. Contact AZEIDK

Sources: Issuing an occupancy certificate (e-service) (Ministry of Municipalities and Housing), Balady enables electronic issuance of building occupancy certificates (Ministry of Municipalities and Housing, 28 September 2026), Issuing an occupancy certificate for a building component (Arabic) (Ministry of Municipalities and Housing), Executive Regulation of the Saudi Building Code Enforcement Law (Arabic PDF) (Ministry of Municipalities and Housing)