Saudi Building Code Enforcement Law and Its Executive Regulation: Owner, Designer and Contractor Duties and the Role of Civil Defense

Saudi Building Code Enforcement Law and Its Executive Regulation: Owner, Designer and Contractor Duties and the Role of

The Saudi Building Code enforcement law and its executive regulation define who applies the code, when, and who answers for it. The regulation requires owners to use licensed designers, supervisors and contractors, bans occupation before an occupancy certificate, gives Civil Defense oversight of fire protection requirements at every stage, and makes the contractor and supervising designer jointly liable for ten years for serious building defects.

This article is based on the regulation text published on the Ministry of Municipalities and Housing website (Ministerial Decision 1213 dated 14/10/1439 AH, as amended up to Decision 00004 dated 8/1/1443 AH) and focuses on what matters for fire systems. For help with Civil Defense requirements on your project, see AZEIDK’s Civil Defense approval support.

Key points

  • Fire protection is one of the code components, and fire safety requirements apply as soon as the regulation is in force, without waiting for the phased schedule.
  • Civil Defense follows up fire code requirements across all construction stages and in maintenance, operation and storage, and appoints inspection bodies in its field.
  • A building permit is issued only after drawings and documents are verified against the code.
  • A building may not be occupied before the occupancy certificate, which states whether fire safety systems are provided.
  • The contractor and supervising designer are jointly liable for ten years from the occupancy certificate for collapse and hidden defects threatening the building’s strength and safety.
In this article
  1. What is the Saudi Building Code enforcement law?
  2. Fire requirements do not wait for the phased schedule
  3. The role of Civil Defense
  4. Responsibilities of owner, designer and contractor
  5. Inspection and the occupancy certificate
  6. Ten-year liability of contractor and supervising designer
  7. What this means for your project
  8. FAQ

What is the Saudi Building Code enforcement law?

The Saudi Building Code is a set of technical codes published by the Saudi Building Code Center, including the general code SBC 201 and the Saudi Fire Protection Code SBC 801; the latest edition listed on the Center’s website is 2024. The enforcement law and its executive regulation are the administrative side: who reviews drawings, who inspects, who issues certificates and who is liable.

The regulation says the code sets minimum safety and public health requirements, including fire protection, and that its parts are applied as one unit. It applies to public and private construction, and to existing buildings when they are repaired, change use, are extended, altered or demolished, following a phased schedule in its annex. The difference between the general code, the fire code and Civil Defense requirements is explained in SBC 801 vs SBC 201 vs Civil Defense requirements.

Fire requirements do not wait for the phased schedule

Thermal insulation and fire safety requirements apply as soon as the regulation is in force, regardless of the phased schedule for the rest of the code. Any new project should therefore design its fire systems to the code from day one.

Existing buildings comply “as far as applicable”, based on a technical report from an approved engineering office describing the feasible solutions. This is the starting point for upgrading fire systems in an existing building, as covered in existing building fire systems assessment.

The role of Civil Defense

The regulation gives the General Directorate of Civil Defense at the Ministry of Interior responsibility for following up fire protection code requirements across all construction stages and in maintenance, operation and storage, including:

  • Monitoring application of the fire protection requirements and recording related violations.
  • Coordinating with the competent authorities to confirm that consultants and contractors are qualified to design, supervise, install, operate and maintain fire systems.
  • Appointing inspection bodies for fire protection.

The municipality, Civil Defense and other authorities appoint inspection bodies in their fields, and the Saudi Standards, Metrology and Quality Organization accredits conformity assessment bodies, including inspection bodies. Later amendments to the inspection bodies regulation are covered in our inspection bodies regulation news.

Responsibilities of owner, designer and contractor

PartyWhat the regulation requiresWhat it means for fire systems
Owner (permit holder)Comply with the code, appoint licensed designers, supervisors and contractors, with contracts that require code complianceHire qualified fire system designers and contractors and name the code in the contract
Approved designerPrepare studies and designs to the code; liable for design defectsFire system drawings and calculations to SBC 801
Supervising designerSupervise works against the permit and approved drawingsFollow installation and tests before handover
ContractorBuild, install, operate and maintain to the codeInstallation to approved drawings, documented tests and as-built drawings
Permit holder at inspectionNotify the inspector when works are ready and provide documents and drawingsPrepare the test file before requesting inspection

Owners, designers and contractors must also contact the municipality on disputes over code interpretation and report violations. The role of engineering offices in safety files is covered in Civil Defense approved engineering offices.

Inspection and the occupancy certificate

Building, repair, alteration, demolition, change of use and extension permits are issued only after documents and drawings are verified against the code. During construction, inspection bodies check application of the code by stage and type, and the authorities may suspend the permit at any stage.

After completion the building may not be occupied until the municipality issues an occupancy certificate. The application includes the permit, final inspection and test approvals and as-built drawings, and the certificate states, among other data, the use and occupancy and whether fire safety systems are provided. A temporary certificate of up to 180 days may be issued for temporary, seasonal and event buildings and for worker housing on large projects during construction. AZEIDK delivers testing and commissioning of fire systems with the records the handover file needs.

Ten-year liability of contractor and supervising designer

The supervising designer and the contractor are jointly liable to compensate the owner for total or partial collapse, or hidden defects that threaten the building’s strength and safety, for ten years from the occupancy certificate date. The liability stands even if the defect comes from the ground itself, and any clause meant to exempt them or limit it is void. A designer whose role was design only is liable for design defects without supervision liability.

This liability concerns the building’s strength and safety; it does not replace the fire system warranty in the supply and installation contract, explained in fire system warranty and acceptance.

What this means for your project

  1. State in the fire systems contract that design and installation follow the Saudi Building Code, and name the edition adopted for the project.
  2. Check the designer’s and contractor’s qualification for fire systems before contracting.
  3. Do not start installation before the drawings are approved within the permit file.
  4. Record every inspection and test during construction; these feed the occupancy certificate.
  5. Hand over complete as-built drawings and O&M manuals.

AZEIDK provides fire system engineering design and calculations, installation and testing, and follows up Civil Defense requirements.

FAQ

What is the difference between the Saudi Building Code and its enforcement law?

The code sets technical requirements such as SBC 801; the enforcement law and regulation set responsibilities, permits, inspection, certificates and violations.

Do fire requirements wait for the phased schedule?

No. Fire safety and thermal insulation requirements apply as soon as the regulation is in force.

What does Civil Defense do under the regulation?

It follows up fire code requirements across all construction stages and in maintenance, operation and storage, acts on violations and appoints inspection bodies in its field.

Can a building be occupied before the occupancy certificate?

No. Occupation is not allowed until the municipality issues the occupancy certificate.

How long is the contractor liable for building defects?

Ten years from the occupancy certificate, jointly with the supervising designer, for collapse and hidden defects threatening strength and safety.

Who appoints fire protection inspection bodies?

Civil Defense appoints inspection bodies for fire protection, and SASO accredits conformity assessment bodies, including inspection bodies.

Can a contract exempt the contractor from the ten-year liability?

No. Any clause meant to exempt the contractor or supervising designer from this liability, or to limit it, is void.

Must an existing building comply with the new code?

When it is repaired, changes use, is extended or altered, and as far as applicable based on a technical report from an approved engineering office.

Starting a new project or altering an existing building? Send us the building type and project stage, and AZEIDK will define the fire systems scope and the documents your permit and handover file need. Contact AZEIDK

Sources: Executive Regulation of the Saudi Building Code Enforcement Law (Arabic PDF) (Ministry of Municipalities and Housing), Saudi Building Code 2024 edition (Saudi Building Code Center)