Low Current Systems Cost for a New Building in Saudi Arabia: What Drives the Price, the BOQ and How to Compare Quotes

Low Current Systems Cost for a New Building in Saudi Arabia: What Drives the Price, the BOQ and How to Compare Quotes

On new buildings, owners and contractors often ask for the low current systems cost as one figure for the building, but it is a set of systems, each priced on different factors: CCTV, access control, networks and Wi-Fi, intercom, public address and the telephone system, plus the fire alarm system they connect to. This guide explains what drives the total cost, how the BOQ is built and how to compare contractor offers, with links to the cost guide for each system.

Key points

  • The cost is a sum of systems, each with its own points, devices and cabling.
  • Shared infrastructure (conduits, trays, telecom rooms and risers) is a large item many people overlook.
  • Timing matters: cabling during construction costs less than changes after finishing.
  • Integration between systems needs programming and coordination and should be its own line item.
  • Compare offers on the same list of systems, the same point counts and the same brands or equivalents.
In this article
  1. Which systems make up the cost?
  2. Shared factors that set the total cost
  3. How the BOQ is built
  4. How to compare low current quotations
  5. How AZEIDK helps
  6. Frequently asked questions
  7. Summary

Which systems make up the cost?

SystemWhat sets its costCost guide
CCTVCamera count, resolution and types, recording period and control roomCCTV cost
Access controlNumber of doors, reader and lock type, softwareAccess control cost
Network and structured cablingPoint count, cable category, risers, racks and testingNetwork cabling cost
Wi-FiAccess point count and generation, switches and licencesWi-Fi network cost
IntercomNumber of flats and monitors, system typeIntercom cost
Public addressSpeakers, zones, amplifier and fire alarm linkPA system price
Telephone systemLines, handsets and licencesIP PBX price
Fire alarmConventional or addressable, point count, cabling and programmingFire alarm system price

Shared factors that set the total cost

  • Building type and use: an office tower, residential compound, school or warehouse each has a different point density.
  • Infrastructure: conduits, cable trays, main and floor telecom rooms and risers between floors. See MDF and IDF telecom rooms in new buildings.
  • Brand tier: brands approved in the project specification or consultant list set the price band.
  • Integration: linking access control to the fire alarm to release doors, linking PA to the fire alarm, and connecting systems to the building management system. See low current integration in smart buildings.
  • Phasing: first-fix cabling during construction, then devices after finishing; a late start means breaking and redoing work.
  • Documentation and handover: shop drawings, as-built drawings, tests and training.

How the BOQ is built

The BOQ works best when split by system, then by item: devices, cabling, infrastructure, installation, programming and testing, with a separate section for shared work such as racks, telecom rooms and UPS units. This lets you compare each system on its own, and drop or defer a system without repricing everything.

How to compare low current quotations

  • Make sure all offers cover the same list of systems and the same point count in each.
  • Check infrastructure: are conduits, trays and risers included or left to the main contractor?
  • Compare brands and classes, and ask for equivalence if the contractor proposes an alternative.
  • Ask about integration, programming and joint testing with the fire alarm system.
  • Ask about warranty, support period and the maintenance contract after handover.

For existing buildings, work usually starts with an assessment of what is installed; see existing low current systems assessment.

Frequently asked questions

How much do low current systems cost for a residential building?

There is no fixed figure. Cost depends on the systems required, points per system, infrastructure, brands and integration. Send the drawings and the list of systems to receive a detailed quotation per system.

When should I request a low current quotation on a project?

Before slab casting and finishing, so conduits and boxes go in the right place. A late start raises costs through breaking and refinishing.

Should I use one contractor or several?

One contractor for connected systems simplifies coordination and integration and makes responsibility clear, but ask for each system to be priced separately so you can compare clearly.

What documents should I send?

Architectural and electrical drawings if available, the list of required systems, approved brands, the city and the planned start date. See what to send with a quote request.

Summary

The cost of low current systems for a new building is a sum of systems, infrastructure and integration. Fix the systems and point counts early, ask for a BOQ split by system, then send your drawings through the AZEIDK quote request form.

Share this article