Fire Alarm Cable Insulation Resistance Testing (Megger): When to Test and How to Read the Result

Fire Alarm Cable Insulation Resistance Testing (Megger): When to Test and How to Read the Result

Fire alarm cable insulation resistance testing (the megger test) measures the insulation resistance between each conductor and earth using a DC test voltage. It is carried out after the cables are pulled and before detectors and the panel are connected. Its purpose is to catch damage done during pulling and fixing before it turns into an earth fault on the panel after handover.

For how conventional and addressable systems compare, see our guide to choosing a fire alarm system for Saudi projects.

This article explains when the test is done and at what voltage, what must be disconnected first, how to read and record the result, and where the test sits in the testing and commissioning sequence on Saudi projects. AZEIDK performs these tests as part of its testing, commissioning and handover service for fire alarm systems.

Key takeaways

  • Insulation testing is done with the cables disconnected from detectors, sounders and the panel, because the test voltage can damage electronics.
  • BS 5839-1 gives a 500 V DC test voltage and a minimum insulation resistance of 2 MΩ between each conductor and earth.
  • A new, healthy cable normally reads far above the minimum. A new cable reading close to 2 MΩ points to a problem worth investigating.
  • The NFPA 72 test-method tables focus on stray voltage, ground faults, short circuits and loop resistance. The megger test is an additional step set by the designer or consultant in the specification.
  • Every reading for every circuit is recorded on a signed test sheet and included in the handover file.
In this article
  1. What is fire alarm cable insulation resistance testing and why is it required?
  2. When should the test be done?
  3. What must be disconnected before a megger test?
  4. Step-by-step procedure
  5. How to read the result
  6. What does NFPA 72 ask for when testing circuit conductors?
  7. Insulation testing versus other cable tests
  8. Common site mistakes
  9. How the test relates to earth faults after handover
  10. AZEIDK’s role in fire alarm testing and commissioning
  11. Frequently asked questions
  12. Conclusion

What is fire alarm cable insulation resistance testing and why is it required?

Fire alarm cable runs a long way: conduit, cable trays, floor penetrations and false ceilings. During pulling, the sheath can be nicked on an unreamed conduit end, crushed under a clip or pierced by a fixing screw. These defects are invisible, and a continuity test will not find them because the conductor itself is intact.

A megger applies a DC voltage higher than the system’s operating voltage, measures the leakage current through the insulation and displays the result in megohms. Good insulation reads very high; damaged or damp insulation reads low. The test catches the problem while the job is still at the containment and cabling stage, when a repair is far easier than after ceilings and finishes are closed.

When should the test be done?

The right moment is after cabling on each loop, zone or circuit is complete, and before detector heads, electronic bases and sounders are fitted and before termination at the panel. Where bases are installed early, agree a safe disconnection method with the supplier, or test before the bases go in.

The test is repeated when:

  • an existing circuit is modified or extended, for example a new floor or relocated devices;
  • a recurring earth fault of unknown origin appears on an existing system, after the suspect circuit is disconnected from the panel;
  • cable routes have been exposed to water, demolition work or a small fire.

Include the test in the inspection and test plan (ITP) and in the method statement for testing and commissioning of the fire alarm system, so the consultant’s engineer can witness and sign the results.

What must be disconnected before a megger test?

Most site damage comes from skipping this step. Addressable detectors, input/output modules, sounders and panel cards contain electronics that will not tolerate the test voltage. So:

  • disconnect the circuit completely from the panel terminals; switching the panel off is not enough;
  • keep detector heads and devices off the circuit during the test, or disconnect their terminals;
  • check the system manufacturer’s instructions, as some specify a lower test voltage or prohibit testing with certain bases fitted;
  • tag the panel and circuit as under test, and inform the facility manager if the building is occupied.

After the test, discharge the cable through the instrument or by briefly connecting the conductors to earth, then reconnect.

Step-by-step procedure

  1. Identify circuits: number each loop, zone and sounder circuit on the drawing so every reading belongs to a known circuit.
  2. Confirm isolation: the circuit is disconnected at both ends and dead, verified with a meter.
  3. Select the voltage: as stated in the specification or by the manufacturer. BS 5839-1 gives 500 V DC for cables whose voltage rating suits it.
  4. Measure: each conductor to earth, conductor to conductor, and each conductor to the screen on screened cable.
  5. Record: log each value with circuit name, approximate length and cable type.
  6. Discharge and reconnect: then test continuity and loop resistance before powering the panel.

How to read the result

According to Professional Electrician, citing clause 38.1 of BS 5839-1, insulation resistance should be at least 2 MΩ between each conductor and earth at 500 V; treat this as a reference value that applies where the project specification adopts BS 5839-1. That is the acceptance floor, not the expected value. A new cable usually reads above the instrument’s range, so a reading near the minimum on new cable suggests damage or moisture.

ReadingLikely meaningAction
Over range or very highHealthy insulationRecord and move to the next circuit
Above the minimum but clearly lower than similar circuitsPossible moisture or partial damageCheck boxes and joints on the route; retest after drying
Below the minimumDamaged insulation or conductor touching earthSplit the circuit and test each section to locate the damage, then repair or replace
Near zeroDirect short to earth or between conductorsFind the screw, clip or cut cable; do not energise until fixed

Comparing circuits of similar length and cable type is useful: a circuit reading well below its neighbours deserves a look even if it passes.

What does NFPA 72 ask for when testing circuit conductors?

The binding rules in the Kingdom are the Saudi Fire Protection Code SBC 801 and Civil Defense requirements; many consultants specify NFPA 72 as the technical reference. The NFPA 72 test-method tables call for checking metallic circuit conductors for stray voltage, ground faults and short circuits, measuring each loop’s resistance against the manufacturer’s limit, and confirming the panel shows a trouble when an open or ground is introduced.

NFPA 72 does not make the megger test mandatory in every case, so it is written into the project specification or requested by the consultant. On projects following British practice, it is a clear part of BS 5839-1. Settle this when the method statement is approved, not after the ceilings are closed.

Insulation testing versus other cable tests

TestWhat it measuresWhat it finds
Insulation resistance (megger)Resistance between conductors and earth at DC voltageDamaged sheath, moisture, contact with metalwork
Continuity and loop resistanceConductor resistance end to endOpen joint or resistance above the manufacturer’s limit
Stray voltage checkUnwanted voltage on the circuitInterference from power cables or wrong connection
Supervision testPanel response to an open or groundThat the panel really monitors the circuit

These tests complement each other. The cable type itself, FPLR or fire-resistant, is settled at material approval; see fire alarm cable types and fire resistance ratings.

Common site mistakes

  • Testing with detectors fitted, damaging bases or panel cards.
  • Taking one reading for a whole loop without opening both ends, so other equipment skews the result.
  • Not testing the screen on screened cable, although accidental contact with metalwork is a common earth-fault cause.
  • Writing “pass” instead of the actual value, so there is no baseline when a fault appears later.
  • Testing on a very humid day after washing or spraying without waiting to dry, then rejecting a good cable.
  • Forgetting to discharge long cable runs after testing.

How the test relates to earth faults after handover

Many earth-fault messages that appear months after handover trace back to insulation damaged during installation. The circuit works at first, then moisture reaches the nick and the fault comes and goes. Recorded megger values for every circuit make the search faster, because the technician compares new readings with the originals. Fault messages are explained in fire alarm panel faults.

AZEIDK’s role in fire alarm testing and commissioning

Under its testing, commissioning and handover service, AZEIDK tests cables and circuits before devices are connected, then tests devices and scenarios, and hands over signed test sheets in the handover file. Where installation is in its scope, this runs alongside installation and implementation. Systems and products are on the fire alarm systems page, and final testing is covered in fire alarm commissioning and testing before handover.

Frequently asked questions

What megger reading should a fire alarm cable give?

BS 5839-1 sets a minimum of 2 MΩ between each conductor and earth at 500 V. A healthy new cable normally reads much higher.

Can I megger test with detectors fitted?

No. Disconnect the circuit from the panel and devices first, because the test voltage can damage electronic components.

Is insulation testing mandatory under NFPA 72?

NFPA 72 tables require checks for stray voltage, ground faults, short circuits and loop resistance. The megger test is usually required by the specification or the consultant.

When should I retest an existing system’s cables?

After circuit changes, after water or demolition damage on the route, or when a recurring earth fault of unknown origin appears.

How is insulation testing different from continuity testing?

Insulation testing finds current leaking through the sheath to earth. Continuity testing finds breaks or high conductor resistance.

Should the screen on screened cable be tested?

Yes, conductors to screen and screen to earth, because accidental screen contact with metalwork is a common earth-fault cause.

Conclusion

Insulation resistance testing is a short item on the programme, but it finds defects that are hard to reach after finishing. Disconnect devices, use the specified voltage, record the actual value for each circuit and compare similar circuits. The system then enters commissioning with clean circuits and a baseline the maintenance team can use later.

Preparing to test a fire alarm system? Send us the drawings, circuit schedule and cable types, and we will set up the test and commissioning plan and the record sheets with you. Contact the AZEIDK team

References: Dr Zzeus Q&A: How do you take an insulation reading on a fire cable? (Professional Electrician, citing BS 5839-1 clause 38.1); Systems Test Mechanics (Electrical Contractor, on the NFPA 72 test-method tables)