FM Global Fire Protection Requirements for Saudi Factories and Warehouses: FM Approved vs FM Data Sheets and How to Close Survey Recommendations

FM Global Fire Protection Requirements for Saudi Factories and Warehouses: FM Approved vs FM Data Sheets and How to

FM Global requirements are the engineering recommendations of the property insurer FM (formerly FM Global), published in its Property Loss Prevention Data Sheets and raised by its field engineers at insured factories and warehouses. They are not the same as the FM Approved mark, which certifies a specific product model, and they bind a facility through the insurance policy rather than the building code.

A plant manager usually meets them as a numbered list in a survey report: increase sprinkler density over a storage area, test the fire pump, supervise control valves. The practical questions follow quickly. What exactly is being asked, how does it relate to the Saudi fire code, and what evidence will the engineer accept to close each item? In most cases the answer starts with an assessment of the existing systems and a defined scope of work, before anything is bought or modified.

Key takeaways

  • FM Global changed its brand name to FM on 17 July 2024. The FM Approvals name and certification mark did not change.
  • FM Approved certifies a product model. FM Data Sheets set design, operation and maintenance criteria for the whole facility.
  • SBC 801, the Saudi Fire Code, is the legal baseline. Insurer requirements are an extra layer that can be stricter.
  • Closing a recommendation needs documented evidence: hydraulic calculations, datasheets for approved models and test results.
  • An approval belongs to the manufacturer’s product model. It does not make a supplier or contractor “FM approved”.
In this article
  1. What are FM Global requirements and who issues them?
  2. FM Approved vs FM Global Data Sheets: what is the difference?
  3. How do insurer requirements relate to SBC 801 and NFPA?
  4. Which FM Data Sheets come up most in survey reports?
  5. What do insurer survey recommendations usually cover?
  6. How do you close survey recommendations step by step?
  7. FM Approved components supplied by AZEIDK GROUP
  8. Common mistakes when responding to a survey report
  9. FAQ
  10. Summary

What are FM Global requirements and who issues them?

FM is a mutual property insurer. On 17 July 2024 it announced an updated brand, moving from FM Global to FM with a new logo and website. Its testing and certification arm, FM Approvals, also refreshed its logo, but its name and certification mark stayed the same and existing certifications were not affected.

The insurer publishes its engineering criteria as Property Loss Prevention Data Sheets. Each one carries a two-part number, such as DS 3-7 for fire pumps, and the series covers design, installation, operation, maintenance and the management of fire protection impairments. Because the market still uses the old name, “FM Global requirements” remains the common phrase in survey reports and project documents.

FM Approved vs FM Global Data Sheets: what is the difference?

Mixing up the two terms causes most of the confusion. An owner may say “our system is FM” because the pump carries the FM Approved mark, while the insurer’s engineer is asking for a design change based on a Data Sheet.

ItemFM ApprovedFM Data Sheets
What it isCertification of a product model tested to an Approval StandardLoss prevention engineering criteria for a facility
Issued byFM ApprovalsFM (the insurer)
Applies toA pump, sprinkler, valve, pipe or supervisory switch of a given model and sizeThe site: sprinkler density, water supply, storage, maintenance, impairment handling
How to verifySearch the model in the Approval GuideCheck the data sheet number and edition quoted in the survey report
Why it bindsProject specification or insurer requirementInsurance policy and the engineer’s recommendations

In practice, installing FM Approved products alone will not close a design recommendation, and meeting the design criteria does not remove the need for approved models where the insurer asks for them. Our guide to UL, FM and LPCB certifications covers the two marks in more depth.

How do insurer requirements relate to SBC 801 and NFPA?

In Saudi Arabia, SBC 801, the Saudi Fire Protection Code, is the legal reference, and drawings and licences go through the General Directorate of Civil Defense. NFPA standards such as NFPA 13 for sprinklers and NFPA 20 for fire pumps are technical references adopted by the designer or written into the project specification.

Insurer requirements sit on top. They neither replace the code nor exempt anyone from it. They can differ from NFPA in how water demand is calculated, how long the water supply must last and what storage heights are allowed, and in some cases they are stricter. The usual rule among designers is to follow the stricter requirement, provided it does not conflict with the Saudi code.

This is a separate matter from the third-party cooperative insurance that Civil Defense requires for licensing certain high-risk activities. That is a regulatory licensing condition, not a property loss prevention survey.

Which FM Data Sheets come up most in survey reports?

A survey report normally cites the data sheet behind each recommendation. Several deal directly with water-based fire protection (titles as listed in FM’s index):

NumberTitleWhen it appears
DS 3-7Fire Protection PumpsFire pump selection, installation and testing
DS 3-26Fire Protection for Nonstorage OccupanciesSprinkler water demand in non-storage areas
DS 3-29Reliability of Fire Protection Water SuppliesReliability of the fire water supply
DS 3-10Private Fire Service Mains and ConnectionsUnderground and site mains and their connections
DS 2-1Corrosion in Automatic Sprinkler SystemsCorrosion in sprinkler piping
DS 8-1Commodity ClassificationClassifying stored goods before choosing storage protection
DS 10-7Fire Protection Impairment ManagementManaging periods when protection is out of service

Storage protection and sprinkler installation have their own data sheets as well. FM revises the series periodically, so check the edition date quoted in the report before starting any calculation. For high-bay storage, see fire protection for warehouses and logistics facilities.

What do insurer survey recommendations usually cover?

Every site is different, but recommendations tend to fall into a few groups:

  • Adequacy of sprinkler protection: the commodity or storage height has changed since the original design, so the density or sprinkler type no longer fits.
  • Water supply and pumps: a performance test compared with the manufacturer’s curve, or proof that the tank covers the required duration.
  • Control valves: confirming that valves are open and either electrically supervised or locked, since one closed valve can disable the whole system.
  • Impairment handling: a written procedure whenever part of the system is shut down for maintenance or alterations.
  • Inspection and maintenance records: documented periodic test results ready for the next visit.

For valve supervision and the link to the fire alarm panel, see Potter waterflow and tamper switches.

How do you close survey recommendations step by step?

  1. Read the recommendation and its reference: identify the data sheet number, edition and clause, and ask the engineer what evidence will close the item.
  2. Collect existing documents: as-built drawings, original hydraulic calculations, datasheets of installed equipment and the latest pump test results.
  3. Assess the system on site: compare reality with the drawings and record storage heights, commodity, pipe and valve condition. This is the core of our existing systems assessment, which ends with a prioritised scope of work.
  4. Recalculate the hydraulics: a new density or design area can change pump and pipe requirements. See sprinkler hydraulic calculations explained, or hand the work to our engineering design and calculations team.
  5. Select approved models: if the insurer requires FM Approved products, check each model and size in the Approval Guide, following our UL, FM and LPCB verification steps.
  6. Coordinate with Civil Defense: any significant change to an approved network should be checked against the code and approval requirements before work starts.
  7. Install, test and document: give the engineer a close-out package with updated calculations, the approved submittal, installation photos and test results.

FM Approved components supplied by AZEIDK GROUP

Through its technical supply service, AZEIDK GROUP supplies components whose models carry FM approval from the manufacturer. Examples include the WATEX WE end suction fire pump, UL listed and FM approved (FM Class 1319 per the product page), and KDI fire sprinkler pipes, UL listed and FM approved. The approval covers the product model and the sizes in the manufacturer’s certificate. It does not mean AZEIDK GROUP itself is FM approved or an FM partner, which is why each supply includes the datasheet and the model’s approval status for checking.

Common mistakes when responding to a survey report

  • Buying FM Approved products before recalculating, then finding the size or density falls short.
  • Relying on an FM logo in a catalogue without checking the model in the Approval Guide.
  • Making a change to meet the insurer without checking it against SBC 801 and Civil Defense approval.
  • Closing an item verbally without documents, so it returns in the next report.
  • Shutting the system down during alterations without a written impairment procedure.

FAQ

Are FM Global requirements legally mandatory in Saudi Arabia?

They are not a statutory code. The legal reference is SBC 801 with Civil Defense approvals. FM requirements bind a facility through its insurance policy and the engineer’s recommendations.

What is the difference between FM Approved and FM Global?

FM Global, now branded FM, is the insurer that issues the Data Sheets. FM Approved is a certification mark granted by FM Approvals to a specific product model after testing.

Is installing FM Approved products enough to close survey recommendations?

Not always. A recommendation may concern design, water supply or maintenance, so it also needs documented calculations and tests alongside approved components.

How do I check that a fire pump is FM approved?

Search the model and size in the FM Approvals Approval Guide and match it with the datasheet and nameplate. Our fire pump UL/FM approval check explains the steps.

Is AZEIDK GROUP FM approved?

No. AZEIDK GROUP supplies products whose models are FM approved by their manufacturers and provides assessment, calculations, supply and installation, without any FM approval or partnership status.

Summary

An insurer’s survey report is not a shopping list. Each recommendation starts with its FM Data Sheet reference, moves through an assessment of what is installed, then calculations and approved components, and ends with documents that prove the item is closed. Following that order spares a factory or warehouse the cost of doing the same modification twice.

Received a survey report from your insurer? Send us the recommendations and the drawings you have, and we will define the scope of work for each item and the calculations and equipment it needs. Contact the AZEIDK GROUP team

Share this article