Progress Payments on Contracting Projects: Advance Payment and Claims in Saudi Fire Protection Contracts

Progress Payments on Contracting Projects: Advance Payment and Claims in Saudi Fire Protection Contracts

Progress payments on contracting projects in Saudi Arabia are the periodic claims a contractor submits to be paid for work actually done, and the advance payment is money released at the start of the contract against a guarantee. On government projects, both are governed by the Government Tenders and Procurement Law and its Implementing Regulation: an optional advance of up to 10% of the contract value against an equal bank guarantee, and progress claims that pass from the consultant to the government entity to the Ministry of Finance within set deadlines. On private projects, all of this is agreed in the contract itself. This article explains the difference for fire protection contracts and what owners and contractors should settle before signing. It ties into AZEIDK general contracting and MEP works.

Key takeaways

  • Government contracts: an advance payment is at the entity’s discretion, not an automatic right. The Implementing Regulation caps it at 10% of the total contract value, released only after an equal guarantee is provided.
  • The advance is recovered in instalments from progress payments starting with the first claim, and its guarantee is reduced as it is recovered.
  • The performance (final) guarantee under the Law is 5% of the contract value, due within 15 working days of the award notice and held until final acceptance.
  • A new Government Tenders and Procurement Law was published in the Umm Al-Qura gazette in September 2026. It takes effect 120 days after publication, and its Implementing Regulation will follow.
  • Private sector: no percentages are fixed by law. Advance, retention and payment periods are negotiated and written into the contract.
In this article
  1. What are progress payments on contracting projects for fire systems?
  2. Advance payment under the government tenders system
  3. How is a progress claim paid on government projects?
  4. Other guarantees linked to payment
  5. What changes under the new 2026 tenders law?
  6. What is usually agreed in private fire protection contracts?
  7. Checklist before signing a contract with progress payments
  8. Where AZEIDK fits in these stages
  9. Frequently asked questions
  10. Conclusion

What are progress payments on contracting projects for fire systems?

A progress claim (also called an interim payment application, or «مستخلص» on Saudi sites) lists the quantities of work completed in a given period, priced at the contract bill of quantities (BOQ) rates. On a fire protection project a claim typically covers metres of installed pipe, number of sprinklers and detectors installed, supply and installation of the fire pump set or fire alarm panel, and later testing and commissioning.

The claim is usually backed by evidence of the work: consultant inspection records, quantity sheets, and test or inspection reports. The final account comes after handover and settles everything, including retention, deductions and variation orders.

Supply contracts versus works contracts

The distinction matters because the government system treats the two differently on some points. Supplying only extinguishers, hoses or spare parts is a supply contract, usually paid after delivery and acceptance. Installing a full sprinkler network or fire alarm system, including supply, installation and commissioning, is a works contract paid through periodic progress claims.

Advance payment under the government tenders system

The Government Tenders and Procurement Law allows the government entity to pay the contractor an advance against a bank guarantee of equal value. The Implementing Regulation sets out the detail:

  • The advance is optional. The wording is that the entity “may” pay it, so a contractor can only claim it if the tender documents or contract provide for it.
  • It is capped at 10% of the total contract value.
  • It is released only after the guarantee is provided. The guarantee must equal the advance and remain valid until the advance is fully recovered.
  • It is recovered from the contractor’s dues in instalments starting with the first claim, at a rate equal to the advance percentage, and the entity instructs the bank to reduce the guarantee as recovery progresses.

In practice, if a 10% advance is paid, 10% is deducted from each progress claim until it is recovered. The cash a contractor receives at the start is offset by smaller payments later, which must be factored in when planning orders for long-lead equipment such as fire pumps and fire alarm panels.

How is a progress claim paid on government projects?

The Implementing Regulation sets a path with a deadline for each party:

  1. The contractor submits the claim after completing part of the work.
  2. The consultant inspects the work and reports within 10 working days of receiving the claim.
  3. The government entity completes approval and sends the payment order to the Ministry of Finance within 15 working days of receiving the consultant’s report.
  4. The Ministry pays within no more than 45 days, according to the consolidated text of the Law and Regulation published by the Ministry of Finance (version 05, June 2026).

If the contractor disputes a deduction, undisputed amounts are still paid. One contested item does not hold up the whole claim.

Final account and retention

Article 111 of the Implementing Regulation, as amended in a notice published in Umm Al-Qura in November 2022, sets the final payment at no less than 10% for public works contracts and 5% for other contracts, released after provisional handover or delivery once the required certificates are submitted. The tender documents and the contract set the details for each project.

Other guarantees linked to payment

ItemGovernment contract (current Law and Regulation)Private contract
Bid (initial) guarantee1% to 2% of the bid valueAs the owner requires, sometimes none
Performance (final) guarantee5% of contract value within 15 working days of award notice, held until final acceptanceAgreed percentage, or replaced by retention
Advance paymentOptional, up to 10% against an equal guaranteeAgreed percentage and guarantee
Claim payment periodSet deadlines for consultant, entity and MinistryAs per contract, stated in days
Price adjustmentOnly in cases set by the Regulation, including rises in certain basic material prices, subject to conditionsAs per contract terms

What changes under the new 2026 tenders law?

The Umm Al-Qura gazette published a new Government Tenders and Procurement Law that replaces the law issued by Royal Decree No. M/128 dated 13/11/1440H. Its Article 101 says it takes effect 120 days after publication in the official gazette. The points that affect payment:

  • Article 64: the entity may pay an advance from the contract value, or the full contract value upfront against an equal bank guarantee, as the Regulation specifies. The Regulation may define cases exempt from the bank guarantee requirement.
  • Article 65: contractor dues are paid as the Regulation specifies.
  • Article 59: the performance guarantee is 5% of contract value, due within 15 working days of the award notice.
  • Article 70: delay penalties are capped at 6% of the value of a supply contract and 15% of other contracts.

Advance percentages and claim deadlines under the new law await its Implementing Regulation. Until then, the signed contract and the tender documents remain the reference for each project. Follow Etimad and the Ministry of Finance for the Regulation’s release.

What is usually agreed in private fire protection contracts?

No law sets an advance percentage or payment period for private owners. Everything is negotiated and depends on project size, the type of equipment and the relationship between the parties. Terms that come up often in supply and installation contracts:

  • Advance payment, with or without a guarantee: common when the project includes imported or made-to-order equipment, since the supplier asks for part of the price at order.
  • Payment on delivery of materials to site: some contracts release a share of the equipment value when it arrives and is inspected, before installation.
  • Monthly claims based on measured work: the most common approach for large networks and systems.
  • Retention: a share held from each claim and released after handover or after the defects liability period.
  • Final payment tied to testing and handover: passing commissioning tests, delivering as-built drawings and O&M manuals, and sometimes completing the Civil Defense requirements for the system.

Where payment depends on an outside approval such as Civil Defense, state in the contract which works and documents fall on the contractor and which fees and building-level requirements fall on the owner, so payment is not held up by something outside the contractor’s scope.

Checklist before signing a contract with progress payments

  • Define the measurement method for each BOQ item. Is pipe measured per linear metre including fittings? Is a sprinkler counted when installed or after the hydrostatic test?
  • Separate supply items from installation items in the BOQ. This makes payment on delivery of materials easier.
  • State the claim approval period and payment period in days, and who signs off for the owner.
  • Tie the final payment to specific documents: test records, as-built drawings, the approved datasheets and submittal, and O&M manuals.
  • Agree variation orders in writing, with a price, before the work is done so they do not become a dispute in the final account.
  • For government work, read the tender documents themselves. They decide whether there is an advance at all.

To understand the roles of manufacturer, distributor, supplier and contractor, which shapes the right contract type, see manufacturer vs distributor vs supplier vs contractor. For the installation stages that progress claims are built on, see fire fighting system installation in Saudi Arabia.

Where AZEIDK fits in these stages

AZEIDK delivers fire fighting and fire alarm systems through its installation and implementation service, followed by testing and commissioning and documentation and final handover, the stages that progress claims and the final payment usually follow. Where a project needs electrical, plumbing and HVAC works together, these are delivered as one integrated package under MEP works. AZEIDK also supports the Civil Defense requirements and approvals linked to the systems.

Frequently asked questions

What is the advance payment percentage on government projects?

The Implementing Regulation of the current law allows the entity to pay an advance of up to 10% of the total contract value against an equal guarantee. It is optional and set by the tender documents.

Is the advance payment the contractor’s right?

No. The text says the entity “may” pay it, so it is the entity’s decision. If the tender documents or contract do not provide for it, it cannot be claimed.

How is the advance recovered from progress claims?

It is deducted in instalments from the contractor’s dues starting with the first claim, at a rate equal to the advance percentage, and the guarantee is reduced with each recovery.

How long does a government progress payment take?

The consultant has 10 working days to report, the entity 15 working days to send the payment order, and the Ministry of Finance then pays within the period in the Regulation (45 days in the updated text on the Ministry’s website).

What is the performance guarantee on government tenders?

5% of the contract value, submitted within 15 working days of the award notice and held until final acceptance. The new 2026 law keeps the same figure.

Is there a mandatory retention percentage in private contracts?

No law sets one for private contracts. Retention, its period and release conditions are negotiated and written into the contract.

When does the new tenders law take effect?

120 days after its publication in the Umm Al-Qura gazette, under its Article 101. Details such as advance percentages await its Implementing Regulation.

Conclusion

On government contracts, the percentages and deadlines are written into the Law and its Regulation: an optional advance of up to 10% against an equal guarantee, a 5% performance guarantee, and a payment path with a deadline for each party. On private contracts none of this is mandatory, so the real protection for both owner and contractor is a clear contract on measurement, approval periods and final payment conditions. With the new law approaching, check each tender’s documents before pricing your bid.

Planning a fire protection project and need a clear BOQ and execution stages? The AZEIDK team reviews the scope with you and proposes stages that payments can be linked to. Talk to the AZEIDK team

References: Government Tenders and Procurement Law (Umm Al-Qura gazette, September 2026, in Arabic); Government Tenders and Procurement Law and its Implementing Regulation, version 05 (Ministry of Finance, June 2026, in Arabic); Amendment of Articles 111 and 127 of the Implementing Regulation of the Government Tenders and Procurement Law (Umm Al-Qura gazette, November 2022, in Arabic).