NFPA 70 is the US National Electrical Code (NEC) for designing and installing electrical wiring, while NFPA 70E is a separate standard for worker safety during electrical work, including arc flash. In Saudi Arabia the mandatory reference for building electrical installations is the Saudi Electrical Code, SBC 401, part of the Saudi Building Code. NFPA 70 is used only as a technical reference when the project specification calls for it.
Key takeaways
- NFPA 70 covers design and installation, NFPA 70E covers safe work practices, and NFPA 70B covers electrical equipment maintenance.
- Current editions: NFPA 70 (2026), NFPA 70E (2027) and NFPA 70B (2026). NFPA 70B changed from a recommended practice to a standard in its 2023 edition.
- SBC 401 is based mainly on the IEC 60364 series and sets a nominal voltage of 230/400 V at 60 Hz.
- Where a foreign reference conflicts with the Saudi Building Code, the Saudi code governs.
- The overlap with fire systems: fire pump power supply, fire alarm panel power sources and alarm cabling.
In this article
- What is NFPA 70 (NEC)?
- How does NFPA 70 relate to SBC 401?
- NFPA 70, 70E, 70B and SBC 401 compared
- NFPA 70 Article 250 and earthing under SBC 401
- NFPA 70E and arc flash safety
- NFPA 70B: electrical equipment maintenance
- Where do these references meet fire protection systems?
- How AZEIDK can help
- Frequently asked questions
- Conclusion
What is NFPA 70 (NEC)?
NFPA 70 is the formal name of the National Electrical Code published by the National Fire Protection Association. It is revised on a three-year cycle, and the latest published edition is 2026. It covers wiring methods, circuit protection, grounding and special equipment. The parts engineers look up most often are:
- NFPA 70 Article 100: definitions, the key to every term used in the code.
- Article 110: general installation requirements, including Section 110.16 on arc-flash hazard warning labels on equipment.
- NFPA 70 Article 250: grounding and bonding.
- Article 695: electrical supply to fire pumps.
- Article 760: fire alarm system circuits.
How does NFPA 70 relate to SBC 401?
The Saudi Building Code includes a dedicated electrical part, the Saudi Electrical Code SBC 401. SASO lists it as “Saudi Electrical Code (SBC 401)” in the scopes of inspection bodies accepted for the Saudi Building Code. According to the electrical requirements guide in the Ministry of Islamic Affairs, Dawah and Guidance technical guides for mosque construction, SBC 401 is based on the IEC 60364 series, covers AC supplies up to 1000 V at 60 Hz, and limits the nominal voltage of installations to 230/400 V. The same guide lists the NEC among its references and states that the Saudi Building Code governs in case of conflict.
In practice, NFPA 70 is not the mandatory building code in Saudi Arabia. Some owners and industrial projects ask for it as an additional reference, but the designer follows SBC 401 first and uses the foreign reference only where it does not conflict. Because the Saudi code follows IEC, its terminology differs from the NEC, which is a frequent source of confusion in drawings and specifications.
NFPA 70, 70E, 70B and SBC 401 compared
| Reference | Subject | Who uses it | Status in Saudi Arabia |
|---|---|---|---|
| SBC 401 | Electrical requirements for buildings | Designers, contractors, inspection bodies | Part of the Saudi Building Code |
| NFPA 70 (NEC) | Design and installation of electrical wiring | Designers, contractors | Technical reference when the specification calls for it |
| NFPA 70E | Safe work practices, shock and arc flash | Employers, operation and maintenance teams | Applies when adopted in the facility’s or owner’s safety policy |
| NFPA 70B | Electrical equipment maintenance | Maintenance teams, facility managers | Applies when adopted in maintenance contracts or policies |
NFPA 70 Article 250 and earthing under SBC 401
The NEC uses the terms grounding and bonding and sets the rules in Article 250. The IEC framework behind SBC 401 uses the term earthing and classifies earthing systems as TN, TT and so on. The guide cited above notes that a safe TN system depends on a reliable connection between protective conductors and earth, and that RCDs should generally be used in TT systems. So do not copy Article 250 details onto a Saudi project’s drawings without checking them against SBC 401, and keep the terminology consistent across the specification and the submittal.
NFPA 70E and arc flash safety
An arc flash is a sudden release of energy between an energized conductor and another conductor or ground, and it can cause severe burns. NFPA 70E protects the worker; it does not govern installation design. Published summaries of changes introduced in the 2024 edition highlight these points (the current edition is 2027, so check its wording for your project):
- Hazard elimination comes first, and the employer must establish and document a procedure for an electrically safe work condition (Article 120).
- Test for absence of voltage at the work location, not upstream.
- Arc flash labels must be durable enough for the environment where they are installed.
- Changes to transformer size, protective devices or their settings can change incident energy results, so the study must be updated.
NFPA 70E arc flash PPE is selected either with the PPE category method or with an incident energy analysis, and the choice is part of the risk assessment for each piece of equipment. We found nothing in the official sources we reviewed that makes NFPA 70E part of SBC 401, so in Saudi Arabia it applies when a facility’s safety policy or the owner’s specification adopts it.
NFPA 70B: electrical equipment maintenance
NFPA 70B used to be a recommended practice. The 2023 edition was issued as a standard, Standard for Electrical Equipment Maintenance, so its wording became requirements rather than recommendations. It ties directly to safety, because the maintenance condition of equipment affects both the likelihood of an arc flash and how fast protective devices clear a fault.
Where do these references meet fire protection systems?
This is where coordination between electrical works and fire systems on the same project matters:
- Fire pumps: the NEC covers them in Article 695, and NFPA 20 covers pump installation. In Saudi Arabia, the guide cited above refers fire pump installations to the fire protection provisions of SBC 801. See our NFPA 20 fire pumps guide.
- Fire alarm panels: the same guide states that the detection and alarm system needs a dedicated supply, with two separate sources, primary and secondary, citing SBC 401 and SBC 801. Explore our fire alarm systems.
- Alarm cables: fire-resistant cable and circuit integrity during a fire are covered in our fire alarm cables and circuit integrity guide.
How AZEIDK can help
AZEIDK delivers MEP works as one integrated package covering electrical, plumbing and HVAC together, not as a standalone electrical contractor, coordinated with the fire fighting systems on the same project. Through our engineering design and calculations service we review the power supply to fire pumps and alarm panels against the Saudi code and the project specification before installation. For what to look for in an MEP contractor on Saudi projects, see our MEP contractors in Saudi Arabia guide.
Frequently asked questions
What is NFPA 70?
It is the US National Electrical Code (NEC) for designing and installing electrical wiring. NFPA revises it every three years, and the latest edition is 2026.
Is NFPA 70 mandatory in Saudi Arabia?
The mandatory code for buildings is the Saudi Electrical Code SBC 401. NFPA 70 is an additional reference when the project specification calls for it, and the Saudi code governs in case of conflict.
What is the difference between NFPA 70 and NFPA 70E?
NFPA 70 sets how wiring is designed and installed. NFPA 70E sets how a worker stays safe on electrical equipment, including arc flash risk assessment and PPE.
What does NFPA 70 Article 250 cover?
Grounding and bonding. On Saudi projects, earthing requirements are checked against SBC 401, which uses IEC terms such as TN and TT systems.
What is NFPA 70 Article 100?
It is the definitions article of the code, the place to check the meaning of any term used in the other chapters.
How is NFPA 70E PPE chosen for arc flash?
Either with the PPE category method or with an incident energy analysis for each piece of equipment, as part of a risk assessment by a qualified person, with a durable label on the equipment showing the result.
What is NFPA 70B?
The standard for electrical equipment maintenance. Since the 2023 edition it is a standard with requirements for those who adopt it, no longer a recommended practice.
Conclusion
NFPA 70, NFPA 70E and NFPA 70B are three US references with different jobs: design and installation, worker safety, and maintenance. For Saudi buildings, SBC 401 remains the basis, and the US references are used when the specification asks for them and they do not conflict. On fire protection projects, the points to watch are fire pump supply, alarm panel power and alarm cabling.
Need the fire pump or fire alarm power supply on your project reviewed? Send the drawings and specification and our engineering team will check them against the Saudi code. Talk to the AZEIDK team
Related guides
- LPCB Certification: What It Means for Fire Protection Equipment
- Fire Systems Handover Documents: As-Built Drawings and O&M Manuals
- Hikvision Access Control: MinMoe Face Terminals, DS-K2801 Controller and Setup with iVMS-4200 and Hik-Connect
- Safety and Fire Fighting Company in Taif: Preparing Hotels, Rest Houses and Shops Before the Civil Defense Inspection