Fire Protection BOQ in Egypt: Writing Alarm, Firefighting, Pump and Extinguisher Items

Fire Protection BOQ in Egypt: Writing Alarm, Firefighting, Pump and Extinguisher Items

A fire protection BOQ (bill of quantities, known in Egypt as the «مقايسة») is the document contractors and suppliers price. If an item just says “fire pump” or “fire alarm panel”, offers differ in scope before they differ in price, and none can be judged fairly.

This guide is for the owner and consultant writing the BOQ: units, descriptions, references and “or approved equal” wording, with sample rows for pumps, alarm, valves, hose reel cabinets and extinguishers from AZEIDK Egypt’s fire fighting solutions.

Key takeaways

  • Every item needs a clear unit, a description of key characteristics, a reference, and a statement of what it includes.
  • “Or approved equal” only protects the owner when the item states what an alternative must meet: duty point, pressure rating, listing status.
  • A fire pump set is priced as one set, pipes by the linear metre, and testing and commissioning usually as a lump sum.
  • Submittals, shop drawings, as-built drawings and operator training belong in separate items, not in the preamble.
  • If the specification requires UL listing or FM approval, write it in the item itself, or you may receive cheaper non-listed offers.
In this article
  1. What a fire protection BOQ does in a tender
  2. The parts of a single BOQ item
  3. Lump sum items and measured items
  4. Sample fire protection BOQ items
  5. What each item should state, system by system
  6. Separate items that are often forgotten
  7. Common mistakes in a fire protection BOQ
  8. How AZEIDK Egypt supports BOQ preparation
  9. Frequently asked questions
  10. Conclusion

What a fire protection BOQ does in a tender

The BOQ is the common basis every bidder prices against, written after design and before tender. It sits between two related steps: budget estimating, covered in fire fighting network cost in Egypt and fire alarm system cost, and comparing the offers once they arrive, covered in comparing fire system quotations.

In Egypt, the binding reference is the Egyptian Code for the Design and Implementation of Fire Protection for Buildings, 2026 edition (Ministerial Decree No. 355 of 2026), with the project drawings approved by the General Directorate of Civil Protection (Ministry of Interior). NFPA standards enter the BOQ as technical references when the specification calls for them. See the 2026 Egyptian fire code.

The parts of a single BOQ item

A complete item answers five questions: what, in what unit, against what reference, which alternatives are acceptable, and what the rate includes:

  1. Item number: numbered by system (1 pumps, 2 valves, 3 alarm).
  2. Description: the equipment type and the characteristics that define its performance, not the product name alone.
  3. Unit: number, set, linear metre or lump sum.
  4. Quantity: from the approved drawings, with the drawing number where possible.
  5. Reference: the specification clause, and the required standard or listing, if any.
  6. Inclusions: supply, installation, connection, programming and testing, or some of them.

The “or approved equal” wording

Naming a model sets the quality level but limits competition to one supplier, so items add “or approved equal, subject to the consultant’s approval”. This only works if the item states the key characteristics an alternative must meet. The US federal acquisition clause FAR 52.211-6 (Brand Name or Equal) shows the same logic, as an example only and not a rule in Egypt: the bidder proves the alternative meets the salient characteristics, names the brand and model, and attaches the technical documents. Write “pump set model X or equal” without flow, pressure, driver type and listing status, and any pump set becomes “equal”.

Lump sum items and measured items

The unit decides how the contractor is paid when quantities change:

Item typeSuitable unitExampleNote
Complete equipment with its componentsSet or numberFire pump set, fire alarm panelList the contents of the set
Repeated devicesNumberDetectors, sounders, hose reel cabinets, extinguishers, valvesPaid on the quantity actually installed
Linear worksLinear metreNetwork pipes, fire alarm cablesState whether fittings, supports and painting are included
Services with one deliverableLump sumTesting and commissioning, submittals, as-built drawings, trainingDefine exactly what must be handed over

Avoid pricing the whole system as one lump sum: every design change then becomes a price dispute.

Sample fire protection BOQ items

Quantities below are illustrative. The models named are AZEIDK Egypt products, each to be read with its datasheet or submittal.

No.Item descriptionUnitQty
1.1Supply and install a complete fire pump set on a common base, duty point 500 GPM at 8 bar, comprising an electric main pump, a diesel standby pump and a jockey pump, with controllers. Non-Listed version, 3PUMP or approved equal. Includes connection to suction and discharge lines, start-up and performance testing of the set.Set1
2.1Supply and install a flanged OS&Y gate valve, 6 in, working pressure not less than 300 psi, AFC A-3000 or approved equal, with a supervisory (tamper) switch wired to the fire alarm panel.No.4
2.2Supply and install a 6 in wet alarm valve station, AFC ACV-300 or approved equal, with the trim approved for the model, including retard chamber, water motor gong, pressure switch, drain valve and pressure gauges.No.2
3.1Supply, install and program an addressable fire alarm panel, number of loops as per drawings with spare capacity, including batteries, Context Plus ZFP or approved equal.No.1
3.2Supply and install an addressable optical smoke detector with base, compatible with the panel, Context Plus or approved equal.No.180
3.3Supply and install an addressable wall/ceiling sounder beacon with built-in short-circuit isolator, to EN 54-3, EN 54-17 and EN 54-23, Context Plus CON451A/CX/SR or approved equal.No.40
4.1Supply and install a red single-door hose reel cabinet with hose reel, hose, nozzle and valve, Falcon Gold FG-1001S or approved equal, connected to the riser.No.16
5.1Supply and install a 6 kg stored-pressure ABC dry powder extinguisher to EN3 and Egyptian standard ES 8442/2021, PYRAMID or approved equal, with wall bracket.No.30
5.2Supply and install a 6 kg CO2 extinguisher to EN3 and Egyptian standard ES 735, PYRAMID or approved equal.No.8

What each item should state, system by system

Fire pumps

State the duty point, set configuration, controller type and required listing status. For example, the datasheet for the 3PUMP set at 500 GPM and 8 bar lists pump model 3P 4×3-10.2 (end suction), a 75 HP electric motor at 415 V and 50 Hz, an 84 HP diesel engine, a jockey pump rated 40 GPM at 8.5 bar, and three individual controllers. 3PUMP duty points available in Egypt are Non-Listed, with UL/FM versions on request, so state any listing requirement in the item, and whether the fuel tank, pump valves and test line are included.

Valves

Write the type, size, end connection and working pressure. The American Fire Control submittals list the flanged A-3000 OS&Y gate valve in 2.5 to 12 in at 300 psi (21 bar) maximum working pressure, and the ACV-300 alarm valve in 2 to 12 in at 300 psi, installed vertically. Name the approved trim: the manufacturer states that changing it voids the listing.

Fire alarm

State the system type (addressable or conventional), the number of loops and spare capacity, batteries, programming and the cause and effect matrix, and interfaces with the pumps, flow switches and valves. Put cables in a separate item by the linear metre. The Context Plus products are part of AZEIDK Egypt’s fire alarm systems, and approvals vary by model, as each datasheet shows.

Hose reel cabinets and extinguishers

The cabinet item lists its contents and whether it is surface mounted or recessed. Falcon Gold cabinets supplied by AZEIDK Egypt are manufactured locally with genuine Falcon Gold components. For extinguishers, state the agent, capacity, fire classes and Egyptian standard, as on the PYRAMID page.

Separate items that are often forgotten

“Rates include testing and handover” in the preamble defines no deliverable. Use separate items:

ItemUnitDeliverable
Material submittalsLump sumDatasheets, certificates and a compliance statement per item, plus replies to consultant comments
Shop drawingsLump sumApproved shop drawings before installation starts
Testing and commissioningLump sum per systemPump performance test, network pressure test, alarm device and scenario tests, with signed reports
As-built drawingsLump sumDrawings matching what was actually installed, in print and electronic form
Operator training and handoverLump sumOperator training on panels and pumps, plus O&M manuals

A fire pump set, for example, is field tested at churn, rated flow and 150% of rated flow, and compared with the certified factory curve, as NFPA 20 based references describe. See fire system commissioning and technical documents for fire fighting equipment.

Common mistakes in a fire protection BOQ

  • Naming the brand only, so any alternative passes or none does.
  • No listing requirement, so listed and non-listed pump sets are compared as one item.
  • “Fire pump” without saying whether it is a complete set or the main pump only.
  • Missing interfaces: valve supervisory switches, flow switches and pump signals to the alarm panel.
  • Pipes and cables with no statement of what the linear metre includes.
  • Quantities that differ between BOQ and drawings, with no clause saying which governs.
  • Testing, training and as-builts folded into one sentence, so some offers drop them.
  • The water tank and civil works with no statement of who carries them out.

How AZEIDK Egypt supports BOQ preparation

Through AZEIDK Egypt services, we review drawings and specifications, propose products for each hazard area with a preliminary take-off, prepare submittals, and handle supply, installation, testing, commissioning, handover and operator training.

Frequently asked questions

What is the difference between a BOQ and a quotation?

The owner or consultant writes the BOQ (items, quantities, specifications). The quotation is the contractor’s or supplier’s priced reply.

Should I name brands in BOQ items?

You can, to show the quality level, as long as you add “or approved equal” with the key characteristics an alternative must meet.

Is a fire pump set written as one item?

Yes, usually as one “set” naming the electric main pump, diesel standby, jockey pump, controllers and what else the item covers.

Must every item be UL listed or FM approved?

The project specification, the consultant and sometimes the insurer decide. Write the requirement into every item it applies to, so offers are comparable.

Where do I put the cost of testing and commissioning?

In a separate item for each system, usually as a lump sum, listing the tests and reports to be handed over.

Can AZEIDK Egypt help with quantities?

Yes. Our consultation and product selection service includes a drawing review and a preliminary quantity take-off. The consultant and owner approve the final BOQ.

Conclusion

A good fire protection BOQ gives every item a unit, key description, reference and inclusions, accepts equal alternatives against defined characteristics, and lists testing, submittals, as-built drawings and training separately. Offers then arrive on one basis, and handover is clearer for everyone.