The 2026 edition of the Egyptian fire code has been in force since the day after its publication in the Official Gazette. Owners and contractors mostly ask how to apply it: what to require in the drawings, what to check in a submittal, and what must be ready when civil protection visits.
This article walks through the project stages in order, from design drawings to maintenance records, and maps the three parts of the code to the systems AZEIDK Egypt delivers under fire fighting systems and fire detection and alarm systems. We keep official facts separate from the good practice we recommend.
Key takeaways
- The new edition was issued by Minister of Housing Decree No. 355 of 2026, published in the Egyptian Official Gazette (Al-Waqa’i Al-Misriya) on 19 May 2026, and took effect the day after publication.
- The code has three parts: structural and architectural requirements, mechanical fire fighting systems, and electrical requirements with detection and alarm systems.
- Each part involves a different team and file. Coordinating them early saves redrawing.
- An official at the Housing and Building National Research Center (HBRC) said the updated code includes checklists that help engineers follow the requirements during construction.
- Installation alone is not enough. A system is only as effective as its periodic maintenance, real testing and the records that prove both.
In this article
- What is officially known about the Egyptian fire code 2026?
- The three parts of the code and the systems they cover
- Stage 1: design drawings
- Stage 2: equipment submittals
- Stage 3: installation on site
- Stage 4: testing, commissioning and handover
- Stage 5: civil protection review before occupancy
- Stage 6: maintenance records after handover
- What if your project started before May 2026?
- Common mistakes when applying the new code
- Frequently asked questions
- Conclusion
What is officially known about the Egyptian fire code 2026?
The full title is the Egyptian Code for the Design and Implementation of Fire Protection for Buildings, 2026 edition. It was prepared by the Housing and Building National Research Center (HBRC) and issued by Ministerial Decree No. 355 of 2026, dated 4 March 2026. It was published in the Official Gazette on 19 May 2026 and replaces the previous edition, known as code 305. Article 49 of Egyptian Building Law No. 119 of 2008 requires permit applicants to apply it.
In statements reported by Al-Mal newspaper in September 2026, Dr. Ahmed Medhat of HBRC said the code sets the minimum safety requirements. Its priority is saving lives, safe evacuation and safe conditions for ambulance and civil protection crews, and installed systems do not guarantee protection without periodic maintenance. There is also a separate Egyptian code for the fire protection of industrial and storage facilities, which HBRC discussed with the Federation of Egyptian Industries, according to the Ministry of Housing portal.
The legal framework is covered in Fire Protection Requirements in Egypt, and the insurance debate in our news report on the fire code and insurers.
The three parts of the code and the systems they cover
The table below maps each part to the related systems and documents, and to the solutions AZEIDK Egypt supplies. The split is an organising aid; the code text and approved drawings govern the details.
| Code part | What it covers on site | Documents you need | What AZEIDK Egypt supplies |
|---|---|---|---|
| Part 1: structural and architectural requirements | Evacuation, emergency exits, stairs and escape routes | Architectural drawings from the consultant | We do not design these, but hose cabinet, call point and extinguisher locations depend on them |
| Part 2: mechanical fire fighting systems | Sprinkler networks, hose cabinets, hydrants, water supply, fire pumps, special suppression and extinguishers | Mechanical drawings, hydraulic calculations, equipment datasheets | AFC valves and hydrants, Falcon Gold hose cabinets, 3PUMP fire pump sets, FM-200/AFC-227 systems, HoodSafer kitchen systems, PYRAMID extinguishers |
| Part 3: electrical requirements, detection and alarm | Alarm panels, detectors, manual call points, sounders and pump power supply | Alarm drawings, cause and effect matrix, battery calculation | Context Plus panels and detectors, TANDA TX7130 beam detector |
Industrial and storage facilities are also subject to their own separate code. For a factory or warehouse, ask the consultant to state which code was applied to each part.
Stage 1: design drawings
Drawings are what civil protection reviews first. Check the following before submission (good practice, not quoted clauses):
- The design basis states clearly that it follows the 2026 edition, not code 305, and names any additional technical reference (such as NFPA 13 or NFPA 72) with its edition.
- The three sets of drawings match each other. The pump room on the mechanical drawing has a power feed on the electrical drawing, and every flow switch and valve tamper switch has a point on the alarm drawing.
- Hydraulic calculations are attached, with the required pump duty point (rated flow and pressure).
- The classification and protection type of each space is fixed, especially electrical rooms, commercial kitchens and stores.
Stage 2: equipment submittals
After drawing approval, a submittal for each item goes to the consultant before purchase. Every item must meet the approved drawings. Each submittal should include:
- The official datasheet of the exact model being supplied, not a general catalogue for the product family.
- The approval or conformity certificate for that same model, such as EN 54 for certain Context Plus models or LPCB for certain TANDA products, as each datasheet states.
- A compliance table comparing each specification or drawing item with what the model provides.
- The manufacturer’s installation and operation instructions.
Examples: 3PUMP sets supplied in the Egyptian market are Non-UL (non-listed), and UL or FM listed versions are available on request, so the specification must say which is required. The HoodSafer kitchen system is approved by the Egyptian General Directorate of Civil Protection and conforms to EN 17446:2021. PYRAMID extinguishers conform to Egyptian standard ES 8442/2021 for dry powder and ES 735 for CO2. More in Fire Equipment Technical Documents in Egypt.
Stage 3: installation on site
Dr. Ahmed Medhat, director of the Structural Physics Research Institute at HBRC, said at the Federation of Industries seminar in October 2026 that the updated code includes checklists to help engineers follow the requirements during construction (Al-Shorouk). Our practical reading: checking the requirements should not wait until the end of the project.
We recommend:
- Build only to the approved drawings kept on site.
- Document any change to routes or locations and take it to the consultant before it is built, not after.
- Receive equipment on delivery and match the model and nameplate against the approved submittal.
- Record partial tests as you go, such as pressure testing each section before ceilings close and insulation testing alarm cables.
Stage 4: testing, commissioning and handover
The main tests to prepare before handover:
| System | Test | Resulting document |
|---|---|---|
| Fire fighting network | Hydrostatic pressure test and flushing | Test report signed by the consultant |
| Fire pump set | Run the electric, diesel and jockey pumps and measure flow and pressure | Actual performance curve against the duty point |
| Fire alarm | Test every detector, call point and sounder, and run the cause and effect scenarios | Device test schedule and a copy of the panel programming |
| Special suppression and kitchen systems | Check installation, manual release and gas or power shut-off as the system requires | Inspection report per manufacturer instructions |
| Extinguishers | Check quantity, type and locations against the drawings | Extinguisher list with serial numbers and fill dates |
The full test list is in Fire System Commissioning and Acceptance. Add as-built drawings, manuals and staff training.
Stage 5: civil protection review before occupancy
The General Directorate of Civil Protection (Ministry of Interior), through its governorate departments, reviews fire protection drawings and systems and inspects before occupancy. Civil protection alone issues the approval. The contractor and supplier hand over a working system and the documents that prove it.
Have on site: approved drawings, signed test reports, submittals and a team able to run the pumps and panel for the inspector. Required documents and timelines vary by facility and governorate, so ask the competent civil protection office early.
Stage 6: maintenance records after handover
HBRC officials stressed that system effectiveness depends on periodic maintenance and, as Al-Shorouk reported, warned that some facilities may not keep their equipment effective after the first years of operation. We have not verified an official published source setting mandatory inspection frequencies, so manufacturer instructions and NFPA 25 (water-based systems) and NFPA 72 (alarm) serve as technical references, not legal requirements.
Good practice is a clear record for every system: a signed report for every visit stating what was checked, what was found and what was repaired, a periodic pump run log per the manufacturer and NFPA 25, extinguisher fill and inspection dates, and the panel’s alarm and fault log. These records are what you can show at any later inspection or when an insurer asks.
What if your project started before May 2026?
We found no official text on a transition period or on projects approved under code 305, so we assume no rule. Ask the competent civil protection office and the consultant in writing which reference your project’s drawings will be reviewed against and file the reply before buying equipment.
Common mistakes when applying the new code
- Submitting drawings prepared under the previous edition without review.
- Treating NFPA as a substitute for the Egyptian code. NFPA standards are technical design references. The legally binding reference is the Egyptian code.
- Keeping the alarm file separate from the fire fighting file. Flow and tamper switches end up unwired.
- Accepting a certificate that does not cover the supplied model. A certificate for a product family is not enough.
- Visual-only maintenance. Without running pumps and testing detectors, readiness is unproven.
Frequently asked questions
What is the decree number of the Egyptian fire code 2026?
It was issued by Minister of Housing Decree No. 355 of 2026, dated 4 March 2026, published in the Official Gazette on 19 May 2026, and took effect the day after publication.
What are the three parts of the code?
Structural and architectural requirements, mechanical fire fighting systems, and electrical requirements with detection and alarm systems. Industrial and storage facilities have a separate code.
Does AZEIDK Egypt issue civil protection approval?
No. Approval is issued by the General Directorate of Civil Protection. We supply, install, test and prepare documents for our equipment.
Do fire pumps have to be UL or FM listed?
The project specification decides. 3PUMP sets supplied in Egypt are non-listed, and listed versions are available on request, so settle this before you sign.
Is an installation certificate enough without maintenance records?
Not in practice. HBRC has stressed that system effectiveness depends on periodic maintenance, and signed records are what prove the system still works.
My project’s drawings were approved under code 305. What should I do?
We found no published official text on transition arrangements, so ask the competent civil protection office and your consultant in writing which reference applies to your project before buying equipment.
Conclusion
The new code changes the reference, not the nature of the work. Projects run smoothly when every party knows its part of the code, the drawings follow the right edition, equipment is approved with documents for the exact model supplied, systems are tested before inspection, and maintenance records are kept after handover. Our services at each of these stages are on the AZEIDK Egypt services page.
Preparing the fire systems file for a new project? Send us the approved drawings or the BOQ, and we will go through the required equipment and its documents for each stage with you. Talk to the AZEIDK Egypt team