A clean agent system does not put out a fire with the agent quantity alone. The room must also hold the concentration long enough. The room integrity test (door fan test) shows whether it will, or whether the agent will leak out through openings nobody noticed.
This article covers hold time, the test method, the report and common failures, with reference to the AFC-227 clean agent system from American Fire Control offered by AZEIDK Egypt.
Key takeaways
- The test predicts agent hold time without a real discharge, using a calibrated fan in the doorway.
- As summarized by specialist sources such as Orr Protection, NFPA 2001 links protection to holding at least 85% of the adjusted minimum design concentration at the highest level of protected contents for at least 10 minutes, or long enough for trained personnel to respond.
- The test procedure sat in Annex C of the 2022 edition of NFPA 2001. In the 2025 edition the “Enclosure Integrity Procedure” is Annex D. In ISO 14520-1:2023 it is Annex E.
- The 10 minutes is a minimum hold period, not the discharge time.
- Most failures come from low-level openings, unsealed cable penetrations and walls that stop at the suspended ceiling instead of the slab.
In this article
- What is a room integrity test and why is it required?
- Hold time: what do the 10 minutes actually mean?
- NFPA 2001 and ISO 14520: where is the test procedure?
- Test steps on site
- Common leakage paths and how they are fixed
- How to read the test report
- When should the test be repeated?
- Common mistakes before and during the test
- Room integrity testing with AFC-227 systems
- Frequently asked questions
- Conclusion
What is a room integrity test and why is it required?
In a total flooding system, the agent quantity is calculated from the room volume and the concentration needed for the hazard. After discharge, the agent starts leaking through cracks and openings, and air takes its place. If leakage is high, the concentration at equipment level drops before ignition sources cool down. The fire can re-ignite even though the system worked.
The room integrity test measures this leakage before any fire happens. A calibrated fan is fitted into the door frame. The room is pressurized and then depressurized by a small amount, and the airflow needed for each pressure difference is recorded. From these readings, the software calculates the Equivalent Leakage Area (ELA) and predicts how long the concentration will stay above the required level. No costly real discharge is needed.
In Egypt, the legally binding reference is the Egyptian Code for the Design and Implementation of Fire Protection for Buildings, 2026 edition (Ministerial Decree No. 355 of 2026), together with the drawings approved by the General Directorate of Civil Protection (Ministry of Interior). The test method and its calculations come from the technical standards named in the project specification, mainly NFPA 2001 and ISO 14520, plus the system manufacturer’s instructions.
Hold time: what do the 10 minutes actually mean?
NFPA 2001 covers this in Section 7.4, Duration of Protection. As summarized by specialist sources such as Orr Protection, a concentration of at least 85% of the adjusted minimum design concentration must remain at the highest level of protected contents in the room for at least 10 minutes. If trained personnel need longer to arrive and deal with the situation, the period is longer.
- The 10 minutes is not the discharge time. Halocarbon agents such as HFC-227ea discharge within seconds. The hold period starts after discharge is complete.
- The protected height decides the result. A heavier-than-air agent leaks out through low openings while clean air enters from above. The boundary between them moves down: the descending interface. The room passes if this interface does not drop below the protected height before the required time ends. The protected height is usually the top of the racks or equipment.
- The period may be longer. The authority or the project specification can ask for more than 10 minutes.
NFPA 2001 and ISO 14520: where is the test procedure?
Many references and reports say the door fan method is in Annex C of NFPA 2001. That is correct for the 2022 edition. But the table of contents of the 2025 edition, the latest, puts the enclosure integrity procedure in Annex D, and Annex C now covers the cup burner method. The 2025 text also lets the authority having jurisdiction require pressurization/depressurization of the enclosure, referring to Annex D.
ISO 14520-1:2023 places the method in Annex E, “Door fan test for determining of minimum hold time”, which is a normative annex. The calculation method and the number of test points have changed between NFPA 2001 editions, so the same room can give a different predicted hold time depending on the edition used.
In practice, the project specification must name the standard and its edition, and the test report must state the edition used for the calculation.
Test steps on site
- Pre-test survey: measure the actual volume, set the protected height, and check doors, openings, ceiling void and raised floor.
- Set the room as it will be at discharge: close the doors and set HVAC and dampers to the state defined by the release sequence in the releasing panel.
- Install the fan in the door frame with a sealed panel and a differential pressure gauge.
- Measure static pressure from wind or HVAC before the fan runs.
- Pressurize and depressurize: run the fan at several pressure points in both directions. The two readings are averaged to reduce the effect of wind and HVAC.
- Calculate: the software uses agent, concentration and heights to give the ELA and predicted hold time.
- Find the leaks if the room fails: use a smoke pencil while the fan runs to find openings, fix them, and retest.
NFPA 2001 (2025 edition) requires the protected enclosure to have the structural strength to contain the discharge, and calls for venting where developed pressures threaten it. According to fire-protection.com.au, the door fan is commonly used with software to assess peak discharge pressure and the vent area needed.
Common leakage paths and how they are fixed
| Leakage path | Why it matters | Typical fix |
|---|---|---|
| Cable and pipe openings at low level and under the raised floor | A heavier-than-air agent escapes from low points first, so the interface drops faster | Seal openings with materials suited to the wall rating, and treat the raised floor as part of the protected volume |
| Walls that stop at the suspended ceiling instead of the slab | The ceiling void connects to other rooms, so air enters easily from above | Extend and seal the wall to the slab, or include the void in the protected volume as designed |
| Doors: gaps at the threshold and frame, no door closer | A continuous gap along most of the door height | Frame gaskets, a sealed threshold and a self-closer, and check the door really closes |
| HVAC ducts and dampers | They stay open if their closure is not tied to the release sequence | Interlock damper closure or HVAC shutdown with the releasing panel and test it during commissioning |
The key is to find these points before test day. Coordinating the electrical, HVAC and fire contractors during finishing saves repeat visits.
How to read the test report
A good report does not just say “pass”. Check that it includes:
- The standard, its edition and the annex used for the calculation.
- The agent, the required concentration and the minimum concentration at the end of the period.
- Room volume and height, and the protected height and how it was set.
- The ELA for pressurization and depressurization, and the measured static pressure.
- Predicted hold time against required hold time, and the state of doors and HVAC during the test.
- Calibration data for the fan and pressure gauge, with dates before the test date.
Mismatched figures, calibration dates after the test date, or a “pass” exactly at the limit should be clarified before acceptance.
When should the test be repeated?
The test is usually done at acceptance, before the system is put in service. After that, according to a Fire Systems Inc. summary that refers to Section 7.4 of NFPA 2001 without naming an edition, the enclosure is inspected every 12 months for new openings or changes that affect leakage or volume, unless an administrative control programme manages any work on walls and ceilings. If enclosure integrity cannot be confirmed after a change, the test is repeated.
Routine maintenance is covered in our article on FM-200 system maintenance.
Common mistakes before and during the test
- Leaving the test to the end, when openings are hidden behind racks.
- Testing with HVAC running or dampers open.
- Using a protected height lower than the actual top of the racks to get a pass.
- Changing the room on site without updating the agent calculation.
- Confusing hold time with discharge time or with the pre-discharge time delay.
- Ignoring the raised floor and the ceiling void when setting the protected volume boundaries.
Room integrity testing with AFC-227 systems
The American Fire Control page at AZEIDK Egypt lists the AFC-227 / AFC-P227 clean agent system for electrical and control rooms. According to the manufacturer’s datasheet, AFC-227 cylinders store liquid HFC-227ea superpressurized with nitrogen. The AFC-P227 version uses a separate nitrogen cylinder to push the agent through longer or more complex pipe networks. The datasheet gives nozzle coverage for enclosure heights from 0.3 to 4.5 m, and states that orifice size is set from the flow calculation program results.
HFC-227ea is heavier than air, so the descending interface model applies and low-level openings are the biggest threat to hold time. For agent selection and the release sequence, see our article on clean agent fire suppression in Egypt. For general handover tests, see fire system commissioning and acceptance. See also special fire suppression and AZEIDK Egypt services.
Frequently asked questions
Does a room integrity test need a real agent discharge?
No. The test uses a fan to measure air leakage, and the software then predicts the hold time by calculation. A real discharge is not part of the test.
Does the agent stay in the room for only 10 minutes?
As specialist summaries of NFPA 2001 put it, the 10 minutes is the minimum period during which at least 85% of the adjusted minimum design concentration must remain at the protected height. The authority may require longer, and the agent keeps leaking out gradually after that.
What happens if the room fails?
Leaks are found while the fan runs, fixed, and the room is retested before acceptance.
Is Annex C of NFPA 2001 the right reference?
It was in the 2022 edition. In the 2025 edition the enclosure integrity procedure is in Annex D. What matters is that the specification names the adopted edition and the report follows it.
Must the test be repeated every year?
According to specialist summaries of NFPA 2001, the usual practice is a yearly inspection of the room for changes or new openings, with a retest when integrity cannot be confirmed. The project specification or the insurer may also ask for periodic retests.
Conclusion
The room integrity test is the practical proof that the room will hold the agent at the protected height for the required time. A pass starts with design and site coordination, and needs a report stating the standard, edition and protected height.
Planning clean agent protection for an electrical or control room? Send us the room dimensions and project specification, and we will review the AFC-227 requirements, datasheet and sealing points with you before installation. Talk to the AZEIDK Egypt team
Related guides
- Fire Protection in Convalescent and Long-Term Care Facilities in Egypt
- Bank Branch Fire Protection in Egypt: Strongrooms, Server Rooms, ATMs and Customer Halls
- AFC ACV-300 Wet Alarm Check Valve in Egypt: Operation and Installation
- Supermarket and Hypermarket Fire Protection in Egypt: Beam Detectors, Extinguishers and Fire Network