Anyone setting up a new factory in Egypt meets one question early, and it cannot wait: how do you get civil protection approval for a factory, first before construction and again before operation? In practice the answer starts with one document that comes back at every stage: the consultant’s fire protection report. It describes the fire water source, the fire pumps, the alarm system, the extinguishers and any gaseous suppression.
This article sets out what that report must contain according to the Golden License Guidebook published by the General Authority for Investment and Free Zones (GAFI) in September 2025, and how to prepare the equipment data so the file does not stall at review. AZEIDK Egypt supplies the equipment behind these items through its fire fighting systems solutions and prepares the submittal files through its technical services.
Key takeaways
- The Golden License Guidebook (September 2025) lists a consultant’s fire protection report, used to obtain civil protection approval for setting up the project, among the building permit documents.
- The license to operate requires approval from the General Directorate of Civil Protection on fire risk prevention requirements.
- The report covers the fire water source, tank capacity, fire pumps, hydraulic calculations, alarm, extinguishers and gaseous suppression for electrical and control rooms.
- The guide requires firefighting equipment to comply with the Egyptian standard, where one exists, or an equivalent international standard, and the project to comply with the Egyptian fire code.
- One license-to-operate condition in the guide: at least 25% of the workforce must receive civil protection training.
In this article
- Where civil protection approval sits in the factory licensing path
- What goes into the report for civil protection approval for a factory
- Water network and fire pumps: where most files get stuck
- Alarm, extinguishers and gaseous suppression in the report
- How to prepare the equipment file before the report is submitted
- Common mistakes
- Frequently asked questions
- Conclusion
Where civil protection approval sits in the factory licensing path
The Golden License is a single, comprehensive approval granted by a Council of Ministers decree. It covers setting up, operating and managing the project, including its building licenses. Its legal basis is Article 20 of Investment Law No. 72 of 2017, as amended by Law No. 160 of 2023, and Articles 41 to 43 of the Executive Regulations. The official guide lists the documents needed at each stage, and civil protection appears twice.
| Stage | What the guide asks for on civil protection | What the equipment team must provide |
|---|---|---|
| Building permit | The fire protection consultant’s report for civil protection approval of the project, a cost sheet of the civil protection works, an inspection fee of 1.5% of that cost, and a fee for the preliminary approval of industrial establishments | An early selection of pumps, valves, alarm and extinguishers with realistic prices for the cost sheet |
| License to operate | Approval of the General Directorate of Civil Protection on fire risk prevention requirements, inspection fees based on the number of typical floors, and workforce training fees | Supply and installation that match the report, documented testing and handover, and an O&M manual |
One point matters here. The cost sheet feeds the inspection fee, so it should be built on an actual equipment selection, not on rough figures that change later.
The guide also requires compliance with the Egyptian fire code. The edition in force now is the Egyptian Code for the Design and Implementation of Fire Protection for Buildings, 2026 edition (Ministerial Decree No. 355 of 2026), effective from the day after its publication in the Egyptian Gazette on 19 May 2026. We covered what it means for owners in our article on the 2026 Egyptian fire code. For how the systems are laid out inside a plant, from the pump room to the electrical rooms, see our guide to factory fire protection.
What goes into the report for civil protection approval for a factory
The guide defines the data the consultant’s report must include. The consultant is a syndicate-registered engineer whose specialty is fire fighting, mechanical or electrical engineering, and the report carries the consultant’s name, contact details and registration certificate. The rest of the report covers these areas:
- Project data: establishment and owner names, address, activity, site boundaries, fire truck access, setbacks and the health and safety officer’s details.
- Land and buildings: total area, occupant load, and each building’s floors, height, use, stairs and exits.
- Hazardous materials: warehouses, stored materials, safety data sheets for chemicals, and the locations of generator and electrical rooms.
- Water network: fire water source, tank capacity by hazard, fire pumps, hydraulic calculations, pressure and flow, pipe sizes, hydrants and valves.
- Alarm: automatic and manual alarm, detector locations, audible and visual signals, signage and emergency lighting.
- Manual extinguishing: extinguisher types, numbers and distribution by hazard.
- Automatic gaseous suppression: for electrical, transformer and control rooms, with calculations and connection to the main panel.
- Ventilation and smoke extraction: natural or mechanical, with smoke extraction linked to the alarm panel.
- General: equipment compliance with standards, an evacuation plan, enough trained staff, the percentage of civil protection works completed, and a site plan and floor plans showing escape routes.
Water network and fire pumps: where most files get stuck
The report asks for numbers, not descriptions: the water source, a tank capacity tied to the hazard, fire pumps with their duty pressure and flow, and hydraulic calculations proving the most remote outlet gets what it needs. These numbers must match the pump set that will actually be delivered.
For projects in Egypt, AZEIDK supplies complete 3PUMP fire pump sets (electric main pump, diesel standby pump, jockey pump and controllers on a common base) at duty points of 500 GPM at 8 bar, 750 GPM at 9 bar, 1000 GPM at 10 bar, 1500 GPM at 10 bar and 1500 GPM at 12 bar. The sets supplied in Egypt are Non-UL (non-listed); UL/FM-listed versions are manufactured and supplied on request. The report and the BOQ should therefore say which type is required, so the delivered set matches what was approved.
On the same network come American Fire Control valves such as the ACV-300 wet alarm check valve and OS&Y gate valves, FW-9000 wet barrel hydrants on the site ring, and Falcon Gold hose reel cabinets, manufactured locally in Egypt with genuine Falcon Gold components, inside the halls.
Alarm, extinguishers and gaseous suppression in the report
Fire alarm
The guide asks for an automatic fire alarm system matched to the hazard, with manual call points and audible and visual signals. In high production halls and warehouses, a beam detector such as the TANDA TX7130 or the Context Plus 55000-268 is usually used instead of many point detectors on a high ceiling. The panel is addressable or conventional depending on plant size: Context Plus ZFP addressable panels or CFP and FP conventional panels, part of our fire detection and alarm solutions.
Extinguishers
The guide asks for extinguisher types, numbers and distribution by hazard, and requires firefighting equipment to comply with the Egyptian standard, where one exists, or an equivalent international standard. PYRAMID extinguishers are a practical example: ABC dry powder units from 1 to 12 kg comply with EN3 and Egyptian standard ES 8442/2021, wheeled units of 25 and 50 kg follow EN 1866 and ES 1494, CO2 units follow EN3 and ES 735, and the EOS-approved products carry the Egyptian quality mark.
Automatic gaseous suppression
The guide names electrical, transformer and control rooms specifically, and asks for calculations and connection to the main panel. This is where the AFC-227 system from American Fire Control fits, within our special fire suppression solutions, with alarm and discharge signals reported to the fire alarm panel.
How to prepare the equipment file before the report is submitted
- Collect data on halls, warehouses, stored materials and safety data sheets before the consultant starts the calculations.
- Confirm the water source and the available tank capacity, then fix the pump duty point after the hydraulic calculation.
- Request the datasheet for every item: pump sets and controllers, valves, hydrants, hose cabinets, alarm panel, detectors and extinguishers.
- Build the civil protection cost sheet on those same items.
- Keep a copy of the approved report with the contractor, because the installation will be inspected against it before the license to operate.
Our article on technical documents for fire equipment explains what goes into a submittal file in detail.
Common mistakes
- Submitting a report with generic pump or tank figures, then delivering a set with a different duty point.
- Stating UL/FM in the report and delivering a non-listed set, or the reverse.
- Leaving electrical and transformer rooms out of the report, although the guide names them.
- Extinguishers without the Egyptian quality mark or a clear certificate of conformity.
- Postponing the evacuation plan and staff training until after start-up, although both are license-to-operate conditions.
- Forgetting to link smoke extraction or the gaseous system to the fire alarm panel.
Frequently asked questions
Who writes the fire protection report for a factory?
A syndicate-registered consultant whose specialty is fire fighting, mechanical or electrical engineering, who states the registration details in the report as the Golden License Guidebook requires.
Is civil protection approval needed only once?
No. The guide lists it among the building permit documents for setting up the project, and then requires approval of the General Directorate of Civil Protection on fire prevention requirements for the license to operate.
What share of workers must be trained?
The guide’s license-to-operate conditions require at least 25% of the industrial establishment’s workforce to receive civil protection training.
Must the fire pumps be UL or FM listed?
The consultant and the project specification decide. 3PUMP sets supplied in Egypt are non-listed; UL/FM-listed versions are supplied on request.
Does the report ask for gaseous suppression in electrical rooms?
The report template in the guide has an item for automatic gaseous suppression of electrical, transformer and control rooms, and the consultant decides whether it is needed based on the hazard.
Which standard applies to extinguishers?
The guide requires firefighting equipment to comply with the Egyptian standard, where one exists, or an equivalent international standard. For portable dry powder extinguishers the Egyptian standard is ES 8442/2021.
Conclusion
Civil protection approval for a factory rests on an accurate consultant’s report, and an accurate report rests on equipment defined by its numbers and documents. When the pumps, valves, alarm and extinguishers match across the report, the BOQ and the delivery, the inspection before the license to operate goes through without surprises.
Preparing a civil protection file for a new plant? Send us the hall areas, the plant activity and the water source, and we will help you select the equipment and prepare the datasheets and submittal files. Talk to the AZEIDK Egypt team