About the project
In Riyadh’s Special Integrated Logistics Zone stands the Kingdom’s first distribution center built specifically for e-commerce: the Global Distribution Center (GDC) of CJ Logistics, one of Korea’s largest logistics groups. The center fulfils orders for iHerb, the global health and wellness retailer, and ships them to customers across the Middle East. At launch, CJ Logistics announced a gross floor area of about 18,000 square metres and a capacity of 15,000 boxes a day. Full operations started with a grand opening ceremony on 12 February 2026.
As demand grew, the center began expanding with a new mezzanine level inside the building, and AZEIDK was appointed fire and life safety contractor for the expansion, with a scope covering supply, installation and maintenance.
Project at a glance
- Facility: CJ Logistics Global Distribution Center, operated for iHerb
- Location: Special Integrated Logistics Zone, Riyadh
- Works: new mezzanine level inside the operating center
- Main contractor: United Smart Matrix
- AZEIDK role: fire and life safety contractor (supply, installation and maintenance)
- Systems: fire fighting pipe network, fire alarm, emergency lighting and exit signs
- Status: in progress
The challenge
E-commerce fulfilment centers are among the hardest buildings to protect from fire: thousands of products in cartons and plastic packaging, operations running around the clock, and many people working between aisles and packing areas. Adding a mezzanine inside an existing building makes it harder still. It changes how sprinkler water reaches the floor below, adds new spaces that detection has to cover, and creates new escape routes that need clear lighting and signs. All of this has to be built while the center keeps shipping orders.
AZEIDK’s solution
Fire fighting pipe network
Pipes are prepared on site to the approved drawings: cut to length, threaded for the smaller sizes, and grooved for the larger sizes so grooved couplings speed up installation and make later maintenance easier. Pipe surfaces are then prepared and painted, and supports are installed with the correct alignment and spacing so the network is properly carried along its full length.
Fire alarm system
Fire alarm conduits and accessories are delivered to site ahead of installation, so detection on the new mezzanine can be connected to the building system and tested with it as one system.
Emergency lighting and exit signs
Emergency lighting and exit signs are installed along the new escape routes from the mezzanine to guide staff to the exits if the normal power supply fails.
Testing, handover and maintenance
After installation the systems are tested and handed over in line with the project requirements, and AZEIDK then maintains them on a regular schedule so they stay ready to work and ready for inspection.
How we run the work in an operating center
- A site team of engineers and technicians with daily supervision on site.
- A daily report to the main contractor and consultant covering work completed, materials received and the manpower on each activity.
- Advance coordination with the client’s engineering team before each stage, with approval requirements prepared before work starts.
- Pipe preparation and painting in set areas of the site to limit the impact on operations.
Why AZEIDK
AZEIDK holds valid High Commission for Industrial Security licences for the installation and maintenance of fire suppression and fire alarm equipment, and is certified to ISO 9001 for quality, ISO 14001 for environment and ISO 45001 for occupational health and safety. For warehouses and distribution centers we deliver the full scope under one contractor: design, supply and installation, testing and handover, then annual maintenance contracts and Civil Defense approvals.
Related services: Installation and implementation · Testing, commissioning and handover · Annual maintenance contracts · Civil Defense approvals · Fire fighting systems · Fire alarm systems · Warehouses and logistics
Planning a similar project?
Our engineers can review your site and recommend the right fire protection, safety and security systems for it.